← AI-DC WebtoonEPISODE 16 · 2026.09.16

Construction costs for the 154 kV feeder line,
Who will bear the costs, and to what extent?

It is risky to assume that “since KEPCO is carrying out the construction, KEPCO will bear all the costs.” First, the supply and demand points and ownership boundaries must be determined, and then the costs must be broken down into KEPCO’s share, facility contribution fees, direct customer costs, and land and permitting fees.

1 cut. 분석가가 154kV 인입선로와 공사비 서류를 보며 비용부담 주체를 묻는 장면
1 / 10 · A scene where an analyst, looking at documents regarding the 154 kV feeder line and construction costs, asks who will bear the costs.
2 cut. 수급지점에서 한전 공급설비와 고객 전기설비의 비용경계를 나누는 장면
2 / 10 · A scene showing the cost boundary between KEPCO’s supply facilities and the customer’s electrical equipment at the supply/demand point
3 cut. 22.9kV 초과 한전소유 특별공급설비와 설계금액 기준 시설부담금을 설명하는 장면
3 / 10 · A scene explaining KEPCO-owned special supply facilities exceeding 22.9 kV and facility contribution fees based on the design cost
4 cut. 고객소유 수전변전소·GIS·변압기·보호·계량설비를 구분하는 장면
4 / 10 · A scene showing the classification of customer-owned power receiving substations, GIS, transformers, protection systems, and metering equipment
5 cut. 사유지 권원·점용허가·굴착·복구 비용을 선로공사와 함께 검토하는 장면
5 / 10 · A scene showing the review of private land title, occupancy permits, excavation, and restoration costs in conjunction with power line construction
6 cut. 상용선로와 예비선로의 별도 설비·경로 비용을 비교하는 장면
6 / 10 · A scene comparing the costs of separate equipment and routes for commercial and reserve power lines
7 cut. 공통 계통보강과 고객 전용설비의 부담범위를 구분하는 회의
7 / 10 · A meeting to distinguish between the scope of responsibility for common grid reinforcement and that for customer-specific facilities
8 cut. 초기 개산견적과 노선·물량·공법 변경을 반영한 최종정산을 비교하는 장면
8 / 10 · A scene comparing the initial rough estimate with the final settlement, which reflects changes in the route, volume, and construction method
9 cut. 한전부담·시설부담금·고객직접비·토지인허가비 네 칸 비용표를 검토하는 장면
9 / 10 · A scene showing a review of the four-column cost table: KEPCO charges, facility charges, customer direct costs, and land and permit fees
10 cut. 소유·수급지점·공사항목·정산조건이 적힌 공식 부담내역서를 확인하는 장면
10 / 10 · A scene showing the verification of an official cost breakdown statement listing ownership, supply/demand points, construction items, and settlement terms
Key Points

Construction costs must be itemized in writing not just by property boundaries but also by “cost categories.”

The first criterion is Supply/Demand Points and Facility Ownership BoundariesA supply point is the location where KEPCO’s power lines or service lines connect to a customer’s electrical equipment. Even for the same 154 kV service line installation project, cost items and schedule responsibilities will vary depending on the location of the supply point, the division between sections owned by KEPCO and those owned by the customer, and the entity commissioning the work.

According to the terminology in KEPCO’s Standard Supply Terms and Conditions, KEPCO-owned dedicated supply facilities intended to supply specific customers and KEPCO-owned extra-high-voltage supply facilities exceeding 22.9 kV are classified as special supply facilities. Facility charges for special supply facilities generally Facility development fees calculated based on the design cost It may be subject to this. One should not interpret that KEPCO bears the full construction cost simply because the facility is owned by KEPCO.

For customer-owned sections, the power receiving substation, GIS, transformers, protective relays, metering, control and communication systems, on-site cabling, and civil and architectural works are budgeted separately as customer project expenses. The total project cost must include not only manufacturing and installation costs but also testing, pre-service inspections, spare parts, operational handover, and maintenance costs.

Costs outside the transmission lines are also separated. Costs outside the transmission line must also be itemized separately. Responsibility for costs related to private land rights and compensation, road and waterway occupancy, excavation, traffic management, restoration, temporary work sites, and access roads may vary depending on the asset owner, project contractor, or permit holder. Linking these costs and payment terms to the land parcel-by-parcel rights registration ledger created in the previous chapter can help reduce omissions.

While a reserve circuit is not simply defined as double the normal operating load, if separate circuits, conduits, circuit breakers, protection devices, meters, or routes are required, additional equipment costs and facility charges may apply. After distinguishing between common grid reinforcement, KEPCO-owned dedicated facilities, and customer-owned service connections, the basis for calculation must be obtained for each.

The preliminary estimate provided in the initial response is not the final settlement amount. The design cost will vary depending on changes to the connection point, actual route, cable length and specifications, civil engineering methods, material unit prices, and public complaints or permit conditions. KEPCO’s share / Facility contribution fee / Customer’s direct construction costs / Land and permitting costs Manage your budget across four categories, and verify VAT, payment due dates, settlement terms, and conditions for refunds or additional charges.

Practical Conclusion: After verifying the supply/demand point, facility ownership, construction items, types of facility contribution fees, and payment/settlement conditions in KEPCO’s official cost breakdown and design calculation basis, you must then combine the customer’s construction contract and the budget for land and permits to determine the total project cost for the 154 kV service connection.

※ This content is intended for initial feasibility and budget review. Actual facility fees and the scope of construction may vary depending on the applicable terms of service, contracted power capacity, supply method, on-site design, and KEPCO’s official calculations; therefore, they must be finalized based on the latest terms and conditions and a written response.

Start site analysis, including the 154 kV service line →
Technical Reference Materials

Please first verify the official definitions of “supply/demand points,” “special supply facilities,” and “facility contribution fees.”

Korea Electric Power Corporation — Definitions of Terms in the Standard Supply Agreement ↗

Korea Electric Power Corporation (KEPCO) ON — Guide to Terms and Conditions for Electricity Use and Supply ↗

National Center for Legal Information — Road Act, Article 61: Road Occupancy Permit ↗

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel