← AI-DC WebtoonEPISODE 15 · 2026.09.15

154 kV transmission line,
What is the scope of the land use consent form?

The correct answer is not the centerline of the power line. For the actual route, all parcels of land affected by permanent facilities, maintenance, and temporary construction zones, as well as roads and waterways, must be managed under a single title registration record obtained through authorization from the relevant administrative agency.

1 cut. 분석가가 여러 필지를 통과하는 154kV 실제 선로경로와 데이터센터를 검토하는 장면
1 / 10 · A scene showing an analyst reviewing the actual 154 kV power line route, which passes through several plots of land, and the data center
2 cut. 직선과 도로·하천·지장물을 피해 우회하는 실제 선로경로를 비교하는 장면
2 / 10 · A scene comparing the actual power line route, which avoids straight lines, roads, rivers, and obstructions
3 cut. 사유지 안의 관로·맨홀·접속함과 유지관리 접근공간을 확인하는 장면
3 / 10 · A scene showing the inspection of pipelines, manholes, junction boxes, and maintenance access areas on private property
4 cut. 굴착구간·작업장·자재적치·장비회전·임시진입로가 포함된 공사현장
4 / 10 · Construction site including excavation sections, work areas, material storage areas, equipment turnaround areas, and temporary access roads
5 cut. 공공도로와 하천을 횡단하며 서로 다른 관리청 허가를 준비하는 장면
5 / 10 · A scene showing preparations for obtaining permits from different regulatory agencies to cross public roads and waterways
6 cut. 지적도·등기부에서 공유·신탁·담보 권리를 필지별로 조사하는 회의
6 / 10 · A meeting to investigate shared, trust, and collateral rights on a parcel-by-parcel basis using cadastral maps and property registries
7 cut. 단기 공사동의서와 장기 지역권·임대 등 안정적인 사용권을 비교하는 장면
7 / 10 · A scene comparing short-term construction consent forms with long-term easements, leases, and other forms of stable usage rights
8 cut. 154kV 수전점에서 한전 구간과 고객소유 구간의 책임경계를 나누는 장면
8 / 10 · A scene showing the demarcation of responsibility between the KEPCO section and the customer-owned section at a 154 kV power receiving point
9 cut. 법무·토지·설계·인허가 담당자가 필지별 권리확보 대장을 검토하는 장면
9 / 10 · A scene showing legal, land, design, and permitting staff reviewing the register of secured rights for each parcel
10 cut. 모든 필지 권리를 확보한 154kV 선로가 데이터센터로 인입되는 장면
10 / 10 · A scene showing a 154 kV power line, for which all land rights have been secured, being connected to the data center
Key Points

The detailed design drawings must align precisely with the rights and permits for each parcel.

If the scope of land use consent is defined by straight-line distance or cable centerline, some parcels will be excluded during the actual construction phase. Since the route shifts due to roads, waterways, and obstructions, elements such as conduits, manholes, junction boxes, and access spaces for inspection and replacement— Permanently used areaIt must be recalculated for each lot in accordance with the as-built drawings.

Excavation width, soil retention, work areas, material storage, equipment maneuvering, temporary access roads, and restoration zones, such as Temporary construction areaThis is distinct from a permanent right of use. Separate agreements are made with the landowner regarding the term, area, compensation, restoration to original condition, and safety responsibilities; if the route changes, the drawings and the annexes to the contract are updated accordingly.

For privately owned land, verify the current owner, co-ownership status, trust status, liens or attachments, lease agreements, and actual authority to dispose of the property based on the land registry and cadastral records. A construction consent form may authorize access for the start of construction, but it does not automatically guarantee long-term operation, inspection, replacement, sale, or financing. Through legal review, we confirm sustainable title rights—such as easements, leases, or purchases—as well as registration and succession conditions aligned with the operational period.

Public roads and waterways require permission from the relevant administrative agency, regardless of land ownership. Article 61 of the Road Act stipulates that permission from the road administration agency is required to install or modify facilities within a road zone or to occupy a road, and the occupation of land or facilities within a waterway zone is also subject to permission under the Waterways Act. Incorporate the following into the schedule: excavation, traffic management, restoration, occupancy fees, permit duration, and coordination with other underground utilities.

A distinction must also be made between the sections of supply facilities owned by KEPCO and those of customer-owned service lines. The boundaries regarding power supply points, facility ownership, construction contracting, and maintenance must be established first so that it becomes clear which entity will secure private property rights and occupancy permits and bear the costs. It should not be assumed that the expropriation procedures for power development projects automatically apply to private customer lines; instead, the applicability must be verified separately based on the operator, facility, and scope of approval.

Register of Secured Rights by Lot: Record the following information, one per line: lot number, owner/rights holder, facility type, permanent/temporary usable area, contract or rights type, licensing authority, compensation/occupancy fees, registration/succession, expiration date, restoration to original condition, availability status, and suspension conditions. If any of the drawings, contracts, or permits change, review the corresponding entries in the same register to ensure consistency.

※ This content is intended for initial feasibility and site reviews. The right to consent regarding jointly owned or trust-held land, structures involving easements, leases, or purchases, the occupation of roads and waterways, and the applicability of power development projects must be confirmed based on actual property registrations and as-built drawings through the latest reviews by attorneys, judicial scriveners, KEPCO, electrical design firms, and relevant regulatory agencies.

Start site analysis, including the 154 kV feeder route →
Technical Reference Materials

Please verify the title to private land separately from the permit for occupation of public areas.

National Law Information Center — Civil Code Article 291: Contents of Easements ↗

National Law Information Center — Road Act, Article 61: Permit for Road Occupancy ↗

Government 24 — Guide to River Occupancy Permit Applications ↗

National Law Information Center — Article 6-2 of the Power Development Promotion Act: Land Expropriation ↗