← AI-DC WebtoonEPISODE 14 · 2026.09.14

154 kV commercial and reserve lines,
If it’s the same conduit, does that mean it’s redundant?

The term “two lines” alone is insufficient. Even if the sources and contracts differ, if they share common conduits, manholes, bridges, power distribution panels, and control power supplies, a single incident could result in the loss of both lines simultaneously.

1 cut. 상용과 예비 두 154kV 케이블이 동일 관로와 맨홀을 공유하는 장면
1 / 10 · A view showing two 154 kV cables—one for commercial use and one for reserve—sharing the same conduit and manhole
2 cut. 서로 다른 공급원에서 출발한 A·B 선로가 현장 경로에서 합쳐지는 장면
2 / 10 · A scene showing lines A and B, originating from different sources, merging along their on-site route
3 cut. 굴착사고가 공용 관로의 두 회선을 동시에 손상시키는 장면
3 / 10 · A scene showing an excavation accident simultaneously damaging two lines in a public utility pipeline
4 cut. 공용 맨홀의 침수와 화재가 두 케이블에 함께 영향을 주는 장면
4 / 10 · A scene showing flooding and a fire in a public manhole simultaneously affecting two cables
5 cut. 변전소부터 구내 수전설비까지 공통고장점을 표시한 경로 지도
5 / 10 · Path map showing common points of failure from the substation to the on-site power receiving facilities
6 cut. 공급원만 다른 구성과 공급원·경로가 모두 분리된 구성을 비교한 장면
6 / 10 · A comparison of a configuration where only the power source differs and a configuration where both the power source and transmission path are completely separate
7 cut. 별도 회랑·관로·맨홀로 데이터센터 양쪽에서 인입하는 두 선로
7 / 10 · Two power lines entering the data center from both sides via separate corridors, conduits, and manholes
8 cut. 두 인입 베이와 보호·제어·통신·절체 인터록을 검증하는 수전설비
8 / 10 · Power receiving equipment that verifies two feed-in bays and the protection, control, communication, and disconnection interlocks
9 cut. 단선결선도·경로도·관로도와 사고 시나리오를 통합 검토하는 회의
9 / 10 · A meeting to conduct a comprehensive review of single-line diagrams, route maps, duct maps, and accident scenarios
10 cut. 독립된 두 154kV 경로가 데이터센터에 인입되고 토지경계를 예고하는 장면
10 / 10 · A scene showing two independent 154 kV lines entering the data center and marking the property boundary
Key Points

Rather than focusing on the number of lines, you should verify whether “they could all be lost simultaneously due to a single incident.”

Even if 154 kV commercial power and reserve power are separate contract items or are supplied from different substations, if the actual power lines pass through the same power corridor, conduit, manhole, bridge, or tunnel, Common Point of Failure (CPF)This remains. This means that while the system can handle failures in the lines themselves, accidents affecting shared sections—such as excavation, fire, flooding, or ground collapse—could cause both lines to go down simultaneously.

In KEPCO’s Standard Supply Terms and Conditions, “Reserve Power (A)” and “Reserve Power (B)” are distinguished based on the supplying substation and voltage conditions. One should not assume, based on these designations alone, that the on-site power lines are physically separated. Contract and supply source distinctions, as well as path independence, must be verified through separate drawings and on-site surveys.

The list of common features does not end with substations. Feeder buses, transmission towers, underground connection points, road crossings, shared utility tunnels, manholes, bridges, on-site service corridors, power receiving bays, circuit breakers, protective relays, DC power supplies for control, communications, and switching interlocks are all shown on a single route diagram. We evaluate, by accident type, whether a single common point could lead to the simultaneous loss of both circuits.

Whenever possible, configure the two circuits using separate corridors, ducts, and manholes, and connect them to different directions of the data center via separate entry bays. For unavoidable crossings or shared sections, strengthen structural protection, fire compartmentation, drainage and flood monitoring, excavation control, and ensure sufficient spare parts and recovery routes. Rather than arbitrarily applying a single separation distance value to all sites, designs should be tailored to the topography, voltage, cables, ownership sections, and accident scenarios.

The final verification consists of drawing reviews and integrated testing. We simulate the following scenarios in sequence—Line A failure, Line B failure, flooding of a shared manhole, cable fire, loss of protective relays and communications, automatic disconnection failure, and re-disconnection after power restoration—to verify whether critical loads can be maintained using UPS systems and generators, as well as to determine the recovery time. The U.S. Department of Energy also explains that a site capable of receiving power from two independent substations enhances reliability.

Working-level submission materials: Review the 154 kV single-line diagram, the supply substation and actual transmission line route map, the plan view of conduits and manholes, the common point of failure register, the protection, control, and communication dependency table, the switching sequence, and the load maintenance and restoration test plans for each type of fault.

※ This content is intended for initial feasibility and site reviews. Actual supply routes, scope of construction, classification of reserve power, protection coordination, and separation and protection conditions must be finalized through KEPCO’s technical review, detailed design by a registered electrical design firm, and consultation with relevant agencies.

Start site analysis, including the 154 kV feeder route →
Technical Reference Materials

Please verify both the source classification and the independence of the actual routes.

Article 63 of the Korea Electric Power Corporation’s General Terms and Conditions of Supply — Reserve Power ↗

National Law Information Center — Korea Electric Power Corporation (KEPCO) Standard Supply Terms and Conditions ↗

U.S. Department of Energy FEMP — Guidelines for Data Center Power Reliability and Independent Substation Review ↗

Start a consultation · Choose a channel