Korea Electric Power Corporation
Notice of Intent → Supply Review and Technical Review → Formal Application and Contract → Supply Construction and Transmission
DATA CENTER DEVELOPMENT / START HERE
From site selection to electricity service application, power system impact assessment, building permits, and operation.
First, we link the contractor to be engaged, the scope of the contract, the documents to be submitted, and the basis for proceeding to the next step.
01 / Overall Schedule
The numbers below indicate the order of project management. Design, power reviews, and permit consultations can be conducted concurrently, and preliminary assessments for each project site must be reflected in the permit schedule first.
Notice of Intent → Supply Review and Technical Review → Formal Application and Contract → Supply Construction and Transmission
Verification of entities subject to assessment and submission of evaluation reports / Consultation on energy usage plans → Revisions and results → Implementation of the agreed-upon plan
Site Selection and Title → Development, Construction, and Related Consultations → Start of Construction → Inspections by Work Type and Occupancy Permit
According to the Enforcement Decree, operators of projects subject to evaluation who must obtain approvals, authorizations, or permits must submit a power system impact assessment report at least three months prior to filing their application. Whether a specific approval is required and whether transitional provisions or exemptions apply are determined based on the project’s history. This period does not guarantee the completion of the entire project.
Verify the entire lot, access roads, zoning classifications, building use classifications, and existing permits. Align the target IT load, final facility power requirements, and initial and expansion schedules into a single project overview.
Prepare the necessary documents with an electrical design firm and submit them to the relevant KEPCO office. Organize information on new contracts, existing contracts, and cumulative capacity increases, and verify whether each is subject to consultation with the Power System Impact Assessment and the Energy Usage Plan.
If the facility is subject to a grid impact assessment, we will submit a separate request to KEPCO for a technical review and respond to the agency’s cost estimates and requests for additional information. If it is not subject to the assessment, we will continue to review the supply plan and negotiate terms with the relevant KEPCO office.
We will combine KEPCO’s response with the business plan and submit the power system impact assessment report to the Ministry of Climate. If the project is subject to consultation on the energy usage plan, we will proceed in parallel with a separate plan. We will manage the timing of submission and consultation prior to applying for project approval.
Development and construction permits are processed after reflecting the results of preliminary consultations and evaluations, as well as the conditions set by relevant agencies. We coordinate with KEPCO regarding formal applications for electricity use, negotiations on supply conditions, and contracts; however, the sequence of these steps for each project is managed separately.
We proceed with detailed design and issue contracts by work category, while carrying out the necessary procedures, such as filing a notice of construction commencement and obtaining approval or filing reports for electrical construction plans. We manage the interfaces between power supply lines and architectural and equipment construction, as well as equipment with long lead times.
We coordinate the as-built drawings, inspections by work category, building occupancy permits, pre-service electrical inspections, and power supply commencement procedures. We consult on the schedules for trial power connection and final power connection based on the actual facility status and inspection conditions.
In accordance with design requirements, we conduct tests simulating power outages, equipment failures, and cooling system malfunctions through a safe, approved procedure and then hand over the facility to the operator. We also ensure compliance with statutory safety management requirements and obligations regarding evaluation and consultation throughout the facility’s operation.
02 / KEPCO · Korea Energy Agency · Climate and Energy
“Jeonpyeong” is an abbreviation for “Power System Impact Assessment.” KEPCO’s technical review provides the input data required for that assessment, and the completed assessment report is submitted by the project owner to the Ministry of Climate, Energy, and Environment. Consultation on energy use plans is a separate system.
Do not focus solely on this application; verify existing contracts and cumulative capacity expansions as well. Even if a project is not subject to a power system impact assessment, separately verify KEPCO’s supply review, consultations on energy usage plans, and building-related procedures.
Verify the capacity specified in the electricity service contract, the target region, the history of new construction and expansions, and whether any statutory exclusions apply. The November 28, 2025, pilot operation guidelines designate the entire country as the target region. Please reconfirm the applicable announcement at the time of submission.
IT load, transformer nameplate capacity (MVA), and daily consumption (kWh) should not be compared directly using a 10 MW benchmark. Determining eligibility or exclusion is not a procedure that the applicant can simply check off and complete on their own.
Korea Electric Power Corporation · Technical Review Team
This is the stage in which KEPCO reviews the impact of large-scale electricity demand on the power grid, and the project owner receives the results to incorporate them into the grid impact assessment report.
First, determine the scope of support for load and power supply plans and technical review applications for electrical design services. Selecting the company to prepare the power system impact assessment at the same time can help minimize omissions when transferring KEPCO’s response to the evaluation report.
View contract scope by provider ↓We examine system equipment overloads following new supply and demand, the resulting increases in load, the time and cost required for reinforcement, and the ability to maintain appropriate voltage levels and ensure a stable power supply. The distance to the nearest substation alone cannot be used as a substitute for these findings.
On November 28, 2025, submit the PDF of the pilot operation application and attachments to the Grid Impact Assessment Division of the Grid Planning Office at KEPCO. After the application is received, fees are paid, and any required revisions are made, the project owner will receive the results of the technical review. Check the original text below for the latest submission address and forms.
After receiving the notice of intent, attach the submitted materials to the application for technical review. A response to the technical review does not immediately constitute an electricity service contract or the completion of power transmission. If supply conditions change, subsequent evaluations, designs, and contract amendments must also be reviewed accordingly.
Ministry of Climate, Energy, and Environment · Power System Impact Assessment
This is the stage where an evaluation report—which combines KEPCO’s technical review materials with the project’s stability, economic benefits, and plans to mitigate grid impacts—is submitted and undergoes policy evaluation and deliberation by the Ministry of Climate.
Specify the scope of the Power System Impact Assessment (PSIA) preparation service, including the review of inclusion and exclusion criteria, technical review support, preparation of the assessment report, submission to the Ministry of Climate, and the process of addressing review comments and incorporating the results. Confirm whether support for electrical design and accounting/tax documentation constitutes a separate service.
View contract scope by provider ↓We distinguish between technical items from KEPCO’s response, non-technical items regarding project stability and economic benefits, and policy items such as power self-sufficiency, policy compliance, and site selection. Since policy decisions are made by agencies and committees, preliminary calculations by private companies are not presented as official review scores or guarantees of approval.
On November 28, 2025, the project operator, Nae-Sang, will submit the evaluation report (HWP) and supporting documentation (PDF) separately to the Grid Operation Innovation Division of the Ministry of Climate. After undergoing policy evaluation, review by the subcommittee, and the Power Policy Deliberation Council, along with any necessary revisions, the operator will receive the results and details of the changes to be implemented. It is not assumed that KEPCO will automatically handle the process through to final acceptance.
For planned ESS, xEMS, and on-site power generation, secure the necessary space, budget, and processes, and prepare all required installation and inspection documentation. As of November 28, 2025, emergency generators and PPA power demand are not included in the on-site power generation capacity. Application criteria and bonus point eligibility will be verified against the original text at the time of submission.
Submitted to the Ministry of Climate, Energy, and Environment · Reviewed by the Korea Energy Agency
This is a separate consultation process that involves not only determining which power source to connect to, but also planning how much energy the facility will consume annually and how to use it efficiently. Even if a facility is not subject to a power system impact assessment, it may still be subject to this consultation.
Enter into a contract with a firm that provides support for the development and coordination of energy usage plans, and specify that electrical, mechanical, and architectural designers must use the same load, operating hours, and cooling conditions. When outsourcing, verify the relevant qualifications, scope of services, and the scope of supplementary and implementation documentation to be prepared.
View contract scope by provider ↓We review the feasibility of energy supply and demand, utilization efficiency, and conservation plans. While a data center’s PUE can be used as an explanatory metric, a single PUE value does not guarantee the completion of negotiations.
Once the project sponsor submits the plan, the Ministry of Climate receives it, followed by review, deliberation, and consultation by the Korea Energy Agency, and then the procedures for supplementary measures, implementation plans, and final reporting. The results of these consultations are incorporated into the building permit, design, construction, and post-construction management.
For the “Facilities” category in the Industrial Complex Guide, the criteria are at least 5,000 toe/year of private fuel or 20 million kWh/year of electricity, and at least 2,500 toe/year of public fuel or 10 million kWh/year of electricity. Separate criteria apply to the “Business” category, which includes cities and industrial complexes. Annual consumption is not determined solely based on a facility’s maximum power capacity.
Review fees announced and billed by KEPCO
Fees for services provided by specialized companies
Customer Costs Under KEPCO’s Terms and Conditions of Service
Construction costs for power supply, power distribution, cooling, and building construction
Separately note whether institutional payments, vendor fees, VAT, actual expenses, and supplementary costs are included. Do not propose the same amount or schedule for projects with different voltages, equipment, or supply plans.
03 / Contract with the Provider
The following is a guide to the division of labor for contract awards. This does not mean that all contracts must be submitted to KEPCO or the Ministry of Climate. Distinguish between legally required registration and licensing tasks and optional consulting services; even if the same company handles multiple tasks, contracts should be drawn up with separate responsibilities and deliverables.
Electrical construction projects are subject to the principle of separate bidding from projects in other industries, and there are also separate bidding regulations for design and supervision services related to these power facilities. For fire safety and information and communications technology (ICT) systems, you must verify the applicable laws and regulations as well as any exceptions. Even if a PM contract is signed, it does not automatically replace the necessary specialized service contracts.
We manage these as contracts that allow us to verify actual work performed, the basis for decisions, and liability for remediation, rather than as contracts that promise permits or supply approvals.
View the list of specialized companies by sector →04 / Review in conjunction with electricity
The items below constitute a checklist for determining applicability. This is not a list of requirements that applies uniformly to all data centers. The responsible designer and the competent authority will finalize the applicable criteria based on the address, area, excavation depth, facilities, and existing permits.
We verify compliance with regulations regarding broadcasting and telecommunications facilities, development activities, conversion of agricultural and forested land, as well as road, height, setback, and zoning plan requirements. For existing buildings, we also verify conditions related to use changes, structural integrity, and disaster prevention.
Information to Retain Land Rights and Site Review Table, Table of Items Subject to Permits, Deliberation, and Agenda Consultation, Permits and Conditions
We review environmental assessments based on project type, area, and location, as well as generator emissions and noise, and cooling water supply and discharge conditions. For water usage, we distinguish between estimated demand and the actual supply response from the water utility.
Information to Retain Scope of application, measurement/forecast data, required assessments, reporting, supply consultations, and mitigation plans
We review flooding and drainage, retaining walls and slopes, excavation and groundwater, and surrounding structures. The historical disaster and geological database is used to determine the scope of on-site surveys and does not replace statutory assessments or drilling surveys.
Information to Retain Review of eligibility, required surveys and assessments, design measures, instrumentation, and emergency response plans
We verify the scope of the traffic impact assessment, access routes and movement paths for large equipment, road occupancy and excavation, and rights of way for access routes, including private land and waterways.
Information to Retain Traffic and route planning; consultations on routes, rights-of-way, and right-of-way/excavation; restoration and cost conditions
We verify generator, fuel, battery, and disaster prevention plans; telecommunications connections; and the relevant construction start and completion dates, pre-operation inspections, and the appointment of safety managers. We determine the responsible personnel and inspection schedules for each facility.
Information to Retain Construction plans, commencement and completion processing, relevant inspection results, and completion and safety management data
The Energy Conservation Plan, as well as certification requirements and obligations regarding distributed energy resources for applicable entities, must be verified separately from the energy use plan consultation. Create application tables based on public/private sector, scale, region, and implementation date.
Information to Retain Target Review Table, Basis for Incorporation into Relevant Plans, Certifications, Installation Plans, and Designs
05 / Proceed to the next step
Rights of Use and Permitted Uses; capacity, voltage, timing, and conditions as specified in KEPCO’s response; list of prior assessments; construction costs and fees; and contract terms in the event of a supply delay
Submissions in which the operator, address, and requested capacity match; results of required power system impact assessments and energy consultations; and the roles and scope of delegation for design and construction
Permit Condition Compliance Checklist, processing of construction plans subject to approval or notification, selection of design, construction, and supervision firms, and KEPCO/customer construction sections and schedules
Pre-operation inspections (including fire safety), building occupancy permits, conditions for commencement of service, handover to safety managers and operations staff, and results of integrated testing for power outages and cooling failures
The pre-operation inspection, building occupancy permit, KEPCO transmission connection, and integrated commissioning each involve different verification processes. Ensure the sequence of these steps is correct in the commissioning plan, and obtain all necessary results before commercial operation begins.
FAQ
“IT Load” refers to the power consumed by IT equipment such as servers, while “power supply” refers to the electricity received from external sources such as KEPCO. ESS stands for Energy Storage System, and xEMS refers to a system that measures and controls a facility’s energy usage. MW denotes power capacity, while kWh and MWh represent the amount of energy consumed over a specific period. PUE is an efficiency metric calculated by dividing the facility’s total energy consumption by its IT energy consumption.
In practice, the first step is to select a design firm to review the architecture, site location, and power demand, and to confirm the necessary evaluations and supply conditions. The construction contractor should be selected before entrusting tasks such as formal application submission, cost estimates, and construction; however, it is not necessary to finalize a contract for all construction work from the outset.
The KEPCO technical review is a stage in which technical data on the power grid is provided. The company preparing the power system impact assessment and the project owner use this response and supporting project documentation to finalize the assessment report, submit it to the Ministry of Climate, and receive the results of the policy evaluation and deliberation. All submission and result documents must be retained.
No. The criteria, review items, and required documentation differ between the power system impact assessment and the energy usage plan consultation. Verify the applicability of each, use the same design input values, but manage the submissions and results separately.
No. A contractor agreement is a contract to handle data preparation and application support, whereas a KEPCO electricity service contract is a power supply contract between the applicant and KEPCO. It is important to distinguish between the authority to submit applications on behalf of others and the party that is the ultimate contracting entity.
November 28, 2025: For the pilot operation, PPA power demand and emergency generators are excluded from the calculation of on-site power generation capacity. Renewable energy, energy efficiency measures, and energy storage systems (ESS) must also be separately verified to ensure they comply with the applicable requirements and standards for installation, operation, and implementation.
We verify compliance with relevant inspections—such as building occupancy permits, pre-service electrical inspections, and fire safety inspections—as well as the commencement of power supply by KEPCO. Following this, we determine when to begin commercial operation after ensuring alignment with operator acceptance criteria, integrated commissioning, and the safety management system.
It varies depending on the site, scope of evaluation, design maturity, grid reinforcement, equipment delivery schedules, and supplementary measures. The agency’s review period is not presented as the total development period; instead, costs—including KEPCO’s review fees, contractor service fees, facility contribution fees, and construction costs—are calculated separately, along with schedules for each prerequisite condition.
Please prepare the address, target IT capacity, planned start date, and any responses or permits you have received from KEPCO. We will organize the necessary reviews and assign responsibilities based on the information provided.
IDC Definition, Data Center Sites, and Power Documentation Guide →
SOURCE NOTES / 2026.09.24
The explanation of the documents and submission process for the Grid Impact Assessment is based on the November 28, 2025, notice regarding changes to the pilot operation and the attached application form. Notice No. 2026-673 was confirmed to be a draft administrative notice and was therefore not applied as a final regulation. You must verify whether the final notice has taken effect and check the latest forms and submission locations before actually submitting an application. The scope of the company’s contract and the phased handover checklist are provided in the AI-DC Practical Guide, which reorganizes this information to suit the project owner’s operations.
Attachment Procedure Guide: Scope, Submission Order, Technical/Non-Technical/Policy Review, Costs, and Implementation Verification. Use the reference date indicated in the pilot operation document.
Verify the provisions effective September 18, 2026. Submit the assessment report at least three months prior to applying for approval of eligible projects.
Applicant, power consumption overview, current status, documents received for scheduled notifications, business registration certificate, etc. This is an attachment to the November 28, 2025, announcement; please reconfirm the latest submission forms.
Verify the current application forms, required documents, and the competent office for formal new applications. Categorize changes and expansions under the appropriate application menu.
Standards by private and public facilities/projects; procedures for submission to the Ministry of Climate, review by the Industrial Complex Corporation, consultation, implementation, and post-implementation management.
Check the relevant services—such as construction plans for private electrical facilities and pre-operation inspections—as well as the application forms and required documents.
Verify the principles and exceptions for separate bidding for electrical construction projects.
Confirm whether separate bids are issued for the design and construction supervision services for the relevant power facilities and identify any exceptions.
Building permits, construction commencement, occupancy permits, and consultations regarding relevant laws and regulations. Verify individual ordinances and project conditions as well.
Draft administrative notice. Do not consider this to be a scoring system that has been finalized, officially announced, or currently in effect.
Verify the applicable provisions for each project, including who is subject to energy use plan consultations and the deadlines for drafting and submitting such plans.
Standards related to land use zones and development activities. Check additional laws and regulations governing individual land types, such as farmland and mountainous land.
Verify the types of environmental assessments and consultation processes based on the project and location.
Verify the applicability of permits and licenses for relevant emission facilities, such as power generation facilities. Separate jurisdictional standards apply to water use and noise.
Confirm consultation with relevant parties, such as those subject to environmental impact assessments.
Verify underground safety assessments and management in accordance with excavation and project conditions.
Scope and consultation for traffic impact assessments. Check regional ordinances as well.
Review matters such as the use of roads for access and exit routes.
Verify fire safety design, construction, and supervision, as well as the reporting and inspection of the relevant construction projects.
Verify relevant obligations, such as information and communications construction, supervision, and pre-service inspections.
Verify the Building Energy Conservation Plan system. Distinguish it from consultations on energy usage plans.
Verify the standards regarding the scope, implementation, modification, and succession of distributed energy facilities and power system impact assessments.