DATA CENTER DEVELOPMENT / START HERE

Before building a data center,
Who should we prepare with, and what should we prepare?

From site selection to electricity service application, power system impact assessment, building permits, and operation.
First, we link the contractor to be engaged, the scope of the contract, the documents to be submitted, and the basis for proceeding to the next step.

01 / Overall Schedule

One Project, Three Parallel Procedures

The numbers below indicate the order of project management. Design, power reviews, and permit consultations can be conducted concurrently, and preliminary assessments for each project site must be reflected in the permit schedule first.

Power Supply

Korea Electric Power Corporation

Notice of Intent → Supply Review and Technical Review → Formal Application and Contract → Supply Construction and Transmission

Assessment and Energy Planning

Ministry of Climate, Energy, and Environment · Korea Energy Agency

Verification of entities subject to assessment and submission of evaluation reports / Consultation on energy usage plans → Revisions and results → Implementation of the agreed-upon plan

Business Licensing

Local Governments and Relevant Agencies

Site Selection and Title → Development, Construction, and Related Consultations → Start of Construction → Inspections by Work Type and Occupancy Permit

  1. 01Summary of Site and Project PlansAddress, Ownership, Size, and Operating Period
  2. 02Notice of Schedule and Confirmation of Affected PartiesQuarter of KEPCO Submission and Evaluation
  3. 03KEPCO Technical ReviewCheck Grid Supply, Overload, and Voltage
  4. 04Power System and Energy ConsultationSubmitted by the project owner → Review and revision
  5. 05Permits and Electricity ContractsProject Approval and Finalization of Supply Terms
  6. 06Design, Procurement, and ConstructionReflect the permit conditions in drawings and contracts
  7. 07Inspection, Operating Permit, and Power TransmissionDistinguish between building, electrical, and fire safety inspections
  8. 08Integrated Commissioning and OperationVerification of Incident Response and Commitment Fulfilment
The power system impact assessment schedule precedes the permit application process.

According to the Enforcement Decree, operators of projects subject to evaluation who must obtain approvals, authorizations, or permits must submit a power system impact assessment report at least three months prior to filing their application. Whether a specific approval is required and whether transitional provisions or exemptions apply are determined based on the project’s history. This period does not guarantee the completion of the entire project.

Sources [1][2]

01Summary of Site and Project PlansAddress, Ownership, Size, and Operating Period

Verify the entire lot, access roads, zoning classifications, building use classifications, and existing permits. Align the target IT load, final facility power requirements, and initial and expansion schedules into a single project overview.

Where to Start
Architectural, urban planning, and civil engineering firms; electrical engineering firms. If overall coordination is required, a development project manager is selected as well.
Documents to be prepared by the project owner
List of land parcel numbers and PNUs, registration and usage rights data, existing permits and drawings, operator information, target capacity, and desired start-up date
Documents to be received from agencies and counterparties
Site review table, basic data for load calculation, list of required permits and evaluations, and verification items by agency
Points to check in the next step
Review the power and permitting preconditions in the land contract and verify whether space can be secured for the electrical room, cooling, and service entrance.

Sources [1][5][9]

02Notice of Schedule and Confirmation of Affected PartiesQuarter of KEPCO Submission and Evaluation

Prepare the necessary documents with an electrical design firm and submit them to the relevant KEPCO office. Organize information on new contracts, existing contracts, and cumulative capacity increases, and verify whether each is subject to consultation with the Power System Impact Assessment and the Energy Usage Plan.

Where to Start
First, select an electrical design firm and contract for the scope of support regarding preliminary notices and technical reviews. For reviews subject to the power system impact assessment, collaborate with the firm preparing the assessment.
Documents to be prepared by the project owner
Information on applicants, operators, and sites; intended use; contracted power, voltage, and commercial/standby circuits by phase; desired start date; and power of attorney for proxy applications
Documents to be received from agencies and counterparties
Basis for receipt of the notice of intent; KEPCO’s response to requests for supplementary information and supply review; documentation confirming inclusion or exclusion from the assessment
Points to check in the next step
A technical review for the power system impact assessment requires a separate application. Do not confuse this with the requirement to first receive a confirmation of availability in response to the notice of intent.

Sources [1][3][4][5]

03KEPCO Technical ReviewCheck Grid Supply, Overload, and Voltage

If the facility is subject to a grid impact assessment, we will submit a separate request to KEPCO for a technical review and respond to the agency’s cost estimates and requests for additional information. If it is not subject to the assessment, we will continue to review the supply plan and negotiate terms with the relevant KEPCO office.

Where to Start
Electrical design firms + power system assessment preparation firms. KEPCO conducts the technical review, while private firms assist with data preparation, submission, and revisions.
Documents to be prepared by the project owner
Technical Review Application, Notice of Intended Action, Business Registration Certificate, evidence of existing progress with KEPCO, and facility plans
Documents to be received from agencies and counterparties
KEPCO Technical Review Response: Availability of supply, overload and voltage issues, difficulty of facility reinforcement, etc.
Points to check in the next step
If there are supply constraints, reinforcement requirements, or specific conditions, review the capacity, voltage, commissioning schedule, and location, and verify the scope of potential changes.

Sources [1][3]

04Power System and Energy ConsultationSubmitted by the project owner → Review and revision

We will combine KEPCO’s response with the business plan and submit the power system impact assessment report to the Ministry of Climate. If the project is subject to consultation on the energy usage plan, we will proceed in parallel with a separate plan. We will manage the timing of submission and consultation prior to applying for project approval.

Where to Start
Companies that prepare power system impact assessments, firms that develop or implement energy usage plans, and electrical and mechanical design firms. Accounting and tax experts should be involved as needed to substantiate project feasibility.
Documents to be prepared by the project owner
KEPCO’s response; rationale for investment, financing, employment, and local government finances; implementation plans for on-site power generation, ESS, and xEMS; annual energy demand and conservation plans
Documents to be received from agencies and counterparties
Documents related to the results of the power system impact assessment review and the implementation of its findings, as well as consultation opinions, implementation plans, and completion status regarding the energy usage plan
Points to check in the next step
Commitments presented during the review shall be reflected in the design, project budget, and schedule, and responsible parties and proof of completion shall be designated.

Sources [1][2][5]

05Permits and Electricity ContractsProject Approval and Finalization of Supply Terms

Development and construction permits are processed after reflecting the results of preliminary consultations and evaluations, as well as the conditions set by relevant agencies. We coordinate with KEPCO regarding formal applications for electricity use, negotiations on supply conditions, and contracts; however, the sequence of these steps for each project is managed separately.

Where to Start
Architects, relevant assessment firms, and electrical design firms. The electrical contractor responsible for supporting the formal application, construction, and inspection processes must be selected prior to the commencement of these tasks.
Documents to be prepared by the project owner
Title deeds, designs, evaluation results, authorization documents, and attachments to the relevant application. Name of the electricity applicant, contracted power, category, supply point, and date of use
Documents to be received from agencies and counterparties
Permits and Consultation Conditions, KEPCO’s Final Supply Conditions, Electricity Usage Contracts, and Facility Contribution Fee Information
Points to check in the next step
Determine the construction schedule and procurement timeline after confirming the scope of work for KEPCO and the customer, the transmission line right-of-way and easement, cost allocation, and the supply date.

Sources [4][9]

06Design, Procurement, and ConstructionReflect the permit conditions in drawings and contracts

We proceed with detailed design and issue contracts by work category, while carrying out the necessary procedures, such as filing a notice of construction commencement and obtaining approval or filing reports for electrical construction plans. We manage the interfaces between power supply lines and architectural and equipment construction, as well as equipment with long lead times.

Where to Start
Legally certified design, construction, and supervision firms. Coordination of responsibilities with cooling, UPS, generator, and telecommunications suppliers, as well as those responsible for commissioning, must begin during the design phase.
Documents to be prepared by the project owner
Permit Condition Compliance Table, Approved Drawings, Construction and Supervision Contracts, Construction Schedule, Equipment Specifications, Safety, Quality, and Commissioning Plans
Documents to be received from agencies and counterparties
Construction commencement applications, documents processing the relevant construction plans, and approved working drawings, inspection reports, and test reports
Points to check in the next step
Review whether design changes lead to permits, evaluations, or amendments to contracts with KEPCO, and gather the supporting documentation required for the final inspection.

Sources [6][7][8][9]

07Inspection, Operating Permit, and Power TransmissionDistinguish between building, electrical, and fire safety inspections

We coordinate the as-built drawings, inspections by work category, building occupancy permits, pre-service electrical inspections, and power supply commencement procedures. We consult on the schedules for trial power connection and final power connection based on the actual facility status and inspection conditions.

Where to Start
Construction, supervision, and design firms; relevant inspection agencies such as the Korea Electrical Safety Corporation; local governments and fire departments with jurisdiction; and KEPCO
Documents to be prepared by the project owner
As-built drawings, supervision and construction completion documents, protection, grounding, and insulation test data, inspection applications and related attachments, and safety management system
Documents to be received from agencies and counterparties
Pre-operation inspection results and inspection certificates for relevant construction work, building occupancy permit, and KEPCO’s basis for commencing power supply
Points to check in the next step
Implement a commissioning plan to verify the integrated operation of power, cooling, control, and emergency power systems even after individual inspections have been passed.

Sources [4][6][9]

08Integrated Commissioning and OperationVerification of Incident Response and Commitment Fulfilment

In accordance with design requirements, we conduct tests simulating power outages, equipment failures, and cooling system malfunctions through a safe, approved procedure and then hand over the facility to the operator. We also ensure compliance with statutory safety management requirements and obligations regarding evaluation and consultation throughout the facility’s operation.

Where to Start
Project owners and operators, commissioning specialists, and design, supervision, and equipment providers. Appoint safety managers appropriate for the facility’s scale and verify the maintenance management system.
Documents to be prepared by the project owner
Integrated commissioning plan, equipment manuals, emergency response procedures, operational staff training, tenant acceptance criteria, and list of compliance documentation
Documents to be received from agencies and counterparties
Commissioning Reports and Action Lists for Unresolved Issues, Completion and Operational Handover Documents, and Evaluation and Energy Plan Implementation Data
Points to check in the next step
When expanding capacity, changing operators, or modifying facilities, re-evaluate whether existing permits, contracts, and assessment conditions need to be amended or carried over.

Sources [1][5][6]

02 / KEPCO · Korea Energy Agency · Climate and Energy

Although the same business materials are used, the submission and review processes are conducted separately.

“Jeonpyeong” is an abbreviation for “Power System Impact Assessment.” KEPCO’s technical review provides the input data required for that assessment, and the completed assessment report is submitted by the project owner to the Ministry of Climate, Energy, and Environment. Consultation on energy use plans is a separate system.

First, verify based on the 10 MW benchmark.

Less than 10 MW

Do not focus solely on this application; verify existing contracts and cumulative capacity expansions as well. Even if a project is not subject to a power system impact assessment, separately verify KEPCO’s supply review, consultations on energy usage plans, and building-related procedures.

Any range that includes exactly 10 MW or more

Verify the capacity specified in the electricity service contract, the target region, the history of new construction and expansions, and whether any statutory exclusions apply. The November 28, 2025, pilot operation guidelines designate the entire country as the target region. Please reconfirm the applicable announcement at the time of submission.

IT load, transformer nameplate capacity (MVA), and daily consumption (kWh) should not be compared directly using a 10 MW benchmark. Determining eligibility or exclusion is not a procedure that the applicant can simply check off and complete on their own.

Sources [1][2][3]

01

Korea Electric Power Corporation · Technical Review Team

Preparing for KEPCO’s Technical Review

This is the stage in which KEPCO reviews the impact of large-scale electricity demand on the power grid, and the project owner receives the results to incorporate them into the grid impact assessment report.

Contracts and finalizations prior to this stage

First, determine the scope of support for load and power supply plans and technical review applications for electrical design services. Selecting the company to prepare the power system impact assessment at the same time can help minimize omissions when transferring KEPCO’s response to the evaluation report.

View contract scope by provider ↓

Supporting Documents to Be Prepared by the Project Owner

  • Information on the applicant organization/corporation or business registration, representative, contact person, and signature/authorization to act on behalf of the organization
  • Location, intended use, target date of operation, history of new construction or expansion, and existing responses from KEPCO
  • Document confirming receipt of the Notice of Intended Power Supply and Business Registration Certificate: Submission materials for the application form attached to the public notice
  • Payment of review fees, submission of supporting documentation, and provision of requested additional materials in accordance with KEPCO’s cost guidelines

Materials to be prepared by a specialized firm

  • Technical review application form listing voltage, MW, commercial/standby circuits, supply/demand points, and installed capacity
  • Load lists and power supply plans aligned with initial, final, and expansion demand, as well as usage dates for each phase
  • Supporting documents for the application, such as single-line diagrams and equipment layout plans, as well as supplementary materials from the organization: The scope of submission will be tailored to the request.
  • A review table summarizing the supply conditions, voltage, and reinforcement requirements in the response, along with the handover copy for the evaluation preparation firm

What does the agency review?

We examine system equipment overloads following new supply and demand, the resulting increases in load, the time and cost required for reinforcement, and the ability to maintain appropriate voltage levels and ensure a stable power supply. The distance to the nearest substation alone cannot be used as a substitute for these findings.

Where do I submit it, and what do I receive in return?

On November 28, 2025, submit the PDF of the pilot operation application and attachments to the Grid Impact Assessment Division of the Grid Planning Office at KEPCO. After the application is received, fees are paid, and any required revisions are made, the project owner will receive the results of the technical review. Check the original text below for the latest submission address and forms.

Submitting a notice of intent and applying for a technical review are separate processes.

After receiving the notice of intent, attach the submitted materials to the application for technical review. A response to the technical review does not immediately constitute an electricity service contract or the completion of power transmission. If supply conditions change, subsequent evaluations, designs, and contract amendments must also be reviewed accordingly.

Sources [1][3][4]

02

Ministry of Climate, Energy, and Environment · Power System Impact Assessment

Preparing the Power System Impact Assessment Report for Submission to the Ministry of Climate

This is the stage where an evaluation report—which combines KEPCO’s technical review materials with the project’s stability, economic benefits, and plans to mitigate grid impacts—is submitted and undergoes policy evaluation and deliberation by the Ministry of Climate.

Contracts and finalizations prior to this stage

Specify the scope of the Power System Impact Assessment (PSIA) preparation service, including the review of inclusion and exclusion criteria, technical review support, preparation of the assessment report, submission to the Ministry of Climate, and the process of addressing review comments and incorporating the results. Confirm whether support for electrical design and accounting/tax documentation constitutes a separate service.

View contract scope by provider ↓

Supporting Documents to Be Prepared by the Project Owner

  • Original response to KEPCO’s technical review, history of scheduled notices, existing contracts, and project permits, as well as supporting evidence for any exclusion claims
  • Business plans, total investment costs, basis for financing, and financial data explaining the project’s stability
  • Basis for calculating figures such as direct employment, investment, and local taxes: Reflects the scope of accounting and tax verification required by the applicable guidelines.
  • Actual data regarding consultations with local governments and community acceptance, as well as the authority to implement plans and project costs

Materials to be prepared by a specialized firm

  • An evaluation report distinguishing between items prepared by KEPCO and those prepared by the project owner, along with a list of supporting documents and a comparison table of figures
  • When proposing on-site power generation, xEMS, or ESS, include capacity, layout, project cost, operating method, installation schedule, and a certificate of compliance.
  • Calculation tables for industrial, employment, and fiscal impacts; evidence to support site selection and policy alignment
  • Review and Supplement Document, Change History, Table of Results Incorporated, and Plan for Submitting Follow-up Supporting Documents (e.g., Installation and Inspection Records)

What does the agency review?

We distinguish between technical items from KEPCO’s response, non-technical items regarding project stability and economic benefits, and policy items such as power self-sufficiency, policy compliance, and site selection. Since policy decisions are made by agencies and committees, preliminary calculations by private companies are not presented as official review scores or guarantees of approval.

Where do I submit it, and what do I receive in return?

On November 28, 2025, the project operator, Nae-Sang, will submit the evaluation report (HWP) and supporting documentation (PDF) separately to the Grid Operation Innovation Division of the Ministry of Climate. After undergoing policy evaluation, review by the subcommittee, and the Power Policy Deliberation Council, along with any necessary revisions, the operator will receive the results and details of the changes to be implemented. It is not assumed that KEPCO will automatically handle the process through to final acceptance.

Even facilities listed solely for scoring purposes are subject to actual implementation.

For planned ESS, xEMS, and on-site power generation, secure the necessary space, budget, and processes, and prepare all required installation and inspection documentation. As of November 28, 2025, emergency generators and PPA power demand are not included in the on-site power generation capacity. Application criteria and bonus point eligibility will be verified against the original text at the time of submission.

Sources [1][2][3][10]

03

Submitted to the Ministry of Climate, Energy, and Environment · Reviewed by the Korea Energy Agency

Preparing for Energy Usage Plan Consultations

This is a separate consultation process that involves not only determining which power source to connect to, but also planning how much energy the facility will consume annually and how to use it efficiently. Even if a facility is not subject to a power system impact assessment, it may still be subject to this consultation.

Contracts and finalizations prior to this stage

Enter into a contract with a firm that provides support for the development and coordination of energy usage plans, and specify that electrical, mechanical, and architectural designers must use the same load, operating hours, and cooling conditions. When outsourcing, verify the relevant qualifications, scope of services, and the scope of supplementary and implementation documentation to be prepared.

View contract scope by provider ↓

Supporting Documents to Be Prepared by the Project Owner

  • Distinction between private and public project sponsors; facility and project types and scales; installation and permitting schedules
  • Conditions for calculating annual electricity and fuel demand; scenarios for initial operation, normal operation, and expansion
  • Overview of supply plans and designs, as well as project costs and schedules for efficiency-improvement facilities

Materials to be prepared by a specialized firm

  • Annual Demand, Supply, and Conservation Plans by Electricity, Heat, and Cooling Systems
  • Comparison of the rationale for proposed solutions and alternative options regarding facility efficiency, control methods, waste heat, and renewable energy
  • Plan for addressing and implementing consultation feedback, a table showing design modifications, and final report and post-project management materials

What does the agency review?

We review the feasibility of energy supply and demand, utilization efficiency, and conservation plans. While a data center’s PUE can be used as an explanatory metric, a single PUE value does not guarantee the completion of negotiations.

Where do I submit it, and what do I receive in return?

Once the project sponsor submits the plan, the Ministry of Climate receives it, followed by review, deliberation, and consultation by the Korea Energy Agency, and then the procedures for supplementary measures, implementation plans, and final reporting. The results of these consultations are incorporated into the building permit, design, construction, and post-construction management.

We determine eligibility by distinguishing between MW and annual kWh.

For the “Facilities” category in the Industrial Complex Guide, the criteria are at least 5,000 toe/year of private fuel or 20 million kWh/year of electricity, and at least 2,500 toe/year of public fuel or 10 million kWh/year of electricity. Separate criteria apply to the “Business” category, which includes cities and industrial complexes. Annual consumption is not determined solely based on a facility’s maximum power capacity.

Sources [5][11]

Please also divide the amount on the quote into four columns.

KEPCO Technical Review Fee

Review fees announced and billed by KEPCO

Design and Evaluation Consulting Fees

Fees for services provided by specialized companies

Facility Surcharge

Customer Costs Under KEPCO’s Terms and Conditions of Service

Customer Facility Construction Costs

Construction costs for power supply, power distribution, cooling, and building construction

Separately note whether institutional payments, vendor fees, VAT, actual expenses, and supplementary costs are included. Do not propose the same amount or schedule for projects with different voltages, equipment, or supply plans.

03 / Contract with the Provider

Which companies should I meet with, when, and to what extent should I entrust them with the work?

The following is a guide to the division of labor for contract awards. This does not mean that all contracts must be submitted to KEPCO or the Ministry of Climate. Distinguish between legally required registration and licensing tasks and optional consulting services; even if the same company handles multiple tasks, contracts should be drawn up with separate responsibilities and deliverables.

01Architectural, Urban Planning, and Civil Engineering Design FirmsBefore reviewing sites and deciding on land contracts · Verify Qualification and Registration Status
Contracts and Verification Documents
Site Review and Design Service Contract. The scope is divided into preliminary review and permitting/detailed design.
Deliverables to be received from the vendor
Review of land use, roads, and layout; table of applicable permits and licenses; master plans and permit schedules
Be sure to include this in the scope of the contract
Scope of additional lots, changes in land use, modifications or transfers of existing permits, and consultations with and supplements from relevant agencies
Points to check during selection
Architect and lead designers by discipline; track record with projects of similar scale and use; responsibility for coordination with other designers
02Electrical design firmsBefore submitting a notice of intent or an application for a KEPCO technical review · Verification of Design Qualifications and Registration
Contracts and Verification Documents
Contract for Electrical Design and Application Support Services + Power of Attorney for Proxy Application
Deliverables to be received from the vendor
Load calculation sheets, initial and final power supply plans, single-line diagrams, application documents, and responses to inquiries from KEPCO
Be sure to include this in the scope of the contract
Distinguish between advance notice and technical review support. Specify whether the project includes changes to contracted power and voltage, as well as detailed design of service lines and power receiving equipment.
Points to check during selection
Responsible for operational capabilities at the specified voltage and scale, scope of registration, and incorporating the results of technical review responses into the design
03Companies that prepare or act as agents for power system impact assessmentsTarget Identification and Technical Review Preparation Phase · Verify agency requirements upon submission
Contracts and Verification Documents
Contract for a Power System Impact Assessment. Distinguish between technical review support and the Ministry of Climate’s assessment report tasks.
Deliverables to be received from the vendor
Scope and Exclusion Review, Technical and Non-Technical Evaluation Reports, List of Supporting Documents, Submitted Documents, Supplementary Documents, and Table of Results Incorporated
Be sure to include this in the scope of the contract
Includes support for KEPCO applications, accounting and tax reviews, the number of times explanations and revisions were provided during deliberations, and whether compliance with conditions and changes were evaluated.
Points to check during selection
November 28, 2025: It was announced that the designation of an agent for the pilot operation would be postponed. At the time of contracting, verify whether the designation system is in effect, as well as the qualifications and responsible personnel; do not rely on the unconfirmed term “officially designated company.”
04Companies involved in the formulation and consultation of energy usage plansAfter confirming the parties involved in the consultation, and before finalizing the design · Verify Requirements for Establishment and Agency Services
Contracts and Verification Documents
Contract for Support in Establishing and Coordinating Energy Usage Plans
Deliverables to be received from the vendor
Annual Energy Demand, Supply, and Efficiency Plans; Supplementary Documents, Implementation Plans, and Final Reports
Be sure to include this in the scope of the contract
Scope ranging from adjusting mechanical and electrical design input values, consulting with the industrial complex, incorporating design changes, to verifying compliance after completion
Points to check during selection
Qualifications and registration requirements for the agency in question; track record of data center load and cooling calculations; and whether the original calculation data is provided
05Accounting, Tax, and Legal ExpertsBefore preparing feasibility studies and investment documentation, and prior to major contracts · Consulting Services Tailored to Your Needs
Contracts and Verification Documents
Contract for business plan review, tax estimates, and legal/contract advisory services
Deliverables to be received from the vendor
Basis for calculating funding, investment, and financial contributions; opinions on the review of contract terms
Be sure to include this in the scope of the contract
The verification format, signatures and seals, level of data verification, and responses to additional inquiries required by the applicable evaluation guidelines
Points to check during selection
Professional qualifications and scope of responsibility. Not all projects require the same advisory agreement to be attached as a statutory attachment.
06Specialized firms in the fields of environment, disaster management, transportation, and geotechnical engineeringAfter the target survey, prior to receiving the preliminary assessment · Verification of Qualifications and Registration Under Relevant Laws and Regulations
Contracts and Verification Documents
Contracts for Surveys and Evaluations by Sector
Deliverables to be received from the vendor
Review of Eligibility, Investigation and Evaluation Reports, and Implementation Table for Supplementary Measures and Consultation Recommendations
Be sure to include this in the scope of the contract
Includes on-site surveys, seasonal and measurement periods, reassessments due to design changes, and whether post-construction surveys are included
Points to check during selection
The ability to link sector-specific registrations, scope of work, and statutory submission and completion deadlines to the overall permitting schedule
07Electrical Contractors and Construction Companies by SectorPrior to formal application submission and related construction work · Review of Construction Contractor Registration and Separate Bidding
Contracts and Verification Documents
Construction Contract + Authorization for Acting as an Agent in Electricity Service Applications
Deliverables to be received from the vendor
Breakdown and Schedule, Construction, Testing, and Completion Documentation, Pre-Operation Inspection and Power Connection Support Materials
Be sure to include this in the scope of the contract
KEPCO/customer property boundaries, scope of service lines and power receiving equipment, whether fees and agency charges are separate, and responsibility for inspection corrections, delays, and defects
Points to check during selection
Distinguish between registered and actual construction personnel, and between the roles of design and supervision. The selection of an electrical contractor is not considered a uniform, statutory prerequisite for the technical review by the Korea Electric Power Corporation (KEPCO).
08Companies Responsible for Statutory Supervision, Commissioning, and OperationSupervision must begin before construction starts, and requirements for commissioning and operation must be addressed from the design phase onward. · Distinction Between Statutory Duties and Performance Verification Contracts
Contracts and Verification Documents
Supervision Service Contract, Integrated Commissioning Contract, Operation and Maintenance Contract
Deliverables to be received from the vendor
Inspection and Supervision Reports, Integrated Test Plans and Results, Operation Manuals, Training, and Handover
Be sure to include this in the scope of the contract
Electrical, mechanical, fire protection, and telecommunications interfaces; responsibility for power outage testing and safety approvals; resolution of outstanding issues; and acceptance criteria
Points to check during selection
Supervisory qualifications and independence; distinction between statutory inspections and private trial operations; responsibilities for appointing operational staff and safety managers
09Landowners, KEPCO, and infrastructure operatorsUpon finalizing the terms for the use and supply of each right, · Ownership and Supply Agreements
Contracts and Verification Documents
Title documents (e.g., land sale, lease, and consent to use), KEPCO electricity service contracts, and relevant water and telecommunications supply contracts
Deliverables to be received from the vendor
Scope and term of use rights; power capacity, voltage, and supply conditions; scope of water and telecommunications services
Be sure to include this in the scope of the contract
Conditions for final payments and contract termination before and after obtaining permits and securing power supply; right-of-way for power lines; contract succession; and liability for delays and costs. Review the binding nature of LOIs and MOUs based on their specific wording.
Points to check during selection
Consistency between the legal rights holder, the contracting party, and the applicant’s name; actual supply agreement. A contract with a construction company does not replace a KEPCO electricity service contract.
10Development PM, CM, Finance, TenantsWhen determining business strategies and investment and operational conditions, · Select based on business structure
Contracts and Verification Documents
Development management contracts, financial agreements, lease and service contracts, etc.
Deliverables to be received from the vendor
Overall schedule, cost, and data management; investment prerequisites; tenant requirements and acceptance criteria
Be sure to include this in the scope of the contract
Selection of specialized contractors, coordination of consultations with agencies, and the boundaries of the project owner’s decision-making, as well as responsibilities, compensation, termination, and handover of data
Points to check during selection
The difference between statutory design and evaluation tasks and coordination tasks. Letters of intent to lease and financial agreements are not listed as common mandatory attachments for KEPCO.
Bulk contracting and statutory separate bidding are different.

Electrical construction projects are subject to the principle of separate bidding from projects in other industries, and there are also separate bidding regulations for design and supervision services related to these power facilities. For fire safety and information and communications technology (ICT) systems, you must verify the applicable laws and regulations as well as any exceptions. Even if a PM contract is signed, it does not automatically replace the necessary specialized service contracts.

Sources [7][8]

Before signing a contract, these six points are documented and agreed upon.

  1. Scope: At what stage is the process—notification of plans, technical review support, evaluation report, deliberation and revisions, or design and construction?
  2. Completion Criteria: Does this refer to the delivery of the report, its receipt, or the process through the submission of revisions and receipt of the results?
  3. Cost of changes: Additional fees apply in the event of changes to the address, capacity, voltage, or operator, or in the event of resubmission or reevaluation.
  4. Responsibility and Deadline: Date the project owner provided the data, date of the company’s deliverables, agency representative responsible for revisions
  5. Fees and Actual Expenses: Whether institutional costs, travel expenses, and VAT are included, and payment terms by phase
  6. Handover: Ownership and usage rights to original drawings, calculations, submitted documents, and responses from agencies, as well as settlement procedures in the event of project termination

We manage these as contracts that allow us to verify actual work performed, the basis for decisions, and liability for remediation, rather than as contracts that promise permits or supply approvals.

View the list of specialized companies by sector →

04 / Review in conjunction with electricity

Even if power is available, separate permits and approvals must be obtained.

The items below constitute a checklist for determining applicability. This is not a list of requirements that applies uniformly to all data centers. The responsible designer and the competent authority will finalize the applicable criteria based on the address, area, excavation depth, facilities, and existing permits.

Architecture, Urban Planning, and Civil Engineering · Jurisdictional Local Government

Construction, Development Activities, and Land Use Conversion

We verify compliance with regulations regarding broadcasting and telecommunications facilities, development activities, conversion of agricultural and forested land, as well as road, height, setback, and zoning plan requirements. For existing buildings, we also verify conditions related to use changes, structural integrity, and disaster prevention.

Information to Retain Land Rights and Site Review Table, Table of Items Subject to Permits, Deliberation, and Agenda Consultation, Permits and Conditions

Sources [9][12]

Environmental, mechanical, and civil engineering experts · Relevant licensing authorities

Environment, Noise, Air Quality, Water

We review environmental assessments based on project type, area, and location, as well as generator emissions and noise, and cooling water supply and discharge conditions. For water usage, we distinguish between estimated demand and the actual supply response from the water utility.

Information to Retain Scope of application, measurement/forecast data, required assessments, reporting, supply consultations, and mitigation plans

Sources [13][14]

Companies specializing in disaster, underground safety, and geotechnical engineering · Relevant agencies

Disasters, Underground Safety, and Ground Conditions

We review flooding and drainage, retaining walls and slopes, excavation and groundwater, and surrounding structures. The historical disaster and geological database is used to determine the scope of on-site surveys and does not replace statutory assessments or drilling surveys.

Information to Retain Review of eligibility, required surveys and assessments, design measures, instrumentation, and emergency response plans

Sources [15][16]

Transportation, Civil Engineering, and Electrical Experts · Local Governments/Road Management Agencies

Crossing Transportation, Roads, and Railways

We verify the scope of the traffic impact assessment, access routes and movement paths for large equipment, road occupancy and excavation, and rights of way for access routes, including private land and waterways.

Information to Retain Traffic and route planning; consultations on routes, rights-of-way, and right-of-way/excavation; restoration and cost conditions

Sources [17][18]

Design, Construction, and Supervision by Sector; Fire Departments/Inspection Agencies

Fire Safety, Information and Communications Technology, and Electrical Safety

We verify generator, fuel, battery, and disaster prevention plans; telecommunications connections; and the relevant construction start and completion dates, pre-operation inspections, and the appointment of safety managers. We determine the responsible personnel and inspection schedules for each facility.

Information to Retain Construction plans, commencement and completion processing, relevant inspection results, and completion and safety management data

Sources [6][19][20]

Architecture and Energy Design Firms · Relevant Review Agencies

Building Energy Standards · Distributed Energy

The Energy Conservation Plan, as well as certification requirements and obligations regarding distributed energy resources for applicable entities, must be verified separately from the energy use plan consultation. Create application tables based on public/private sector, scale, region, and implementation date.

Information to Retain Target Review Table, Basis for Incorporation into Relevant Plans, Certifications, Installation Plans, and Designs

Sources [21][22]

05 / Proceed to the next step

Instead of saying “That’s fine,” please check the document you received.

Before signing a site lease or making an investment decision

Rights of Use and Permitted Uses; capacity, voltage, timing, and conditions as specified in KEPCO’s response; list of prior assessments; construction costs and fees; and contract terms in the event of a supply delay

Prior to applying for a permit or formal electricity service

Submissions in which the operator, address, and requested capacity match; results of required power system impact assessments and energy consultations; and the roles and scope of delegation for design and construction

Before construction begins or equipment is ordered

Permit Condition Compliance Checklist, processing of construction plans subject to approval or notification, selection of design, construction, and supervision firms, and KEPCO/customer construction sections and schedules

Prior to transmission and commercial operation

Pre-operation inspections (including fire safety), building occupancy permits, conditions for commencement of service, handover to safety managers and operations staff, and results of integrated testing for power outages and cooling failures

The pre-operation inspection, building occupancy permit, KEPCO transmission connection, and integrated commissioning each involve different verification processes. Ensure the sequence of these steps is correct in the commissioning plan, and obtain all necessary results before commercial operation begins.

FAQ

Frequently Asked Questions When Preparing to Launch a Business

What do “IT Load,” “Power Supply,” “ESS,” and “xEMS” mean?

“IT Load” refers to the power consumed by IT equipment such as servers, while “power supply” refers to the electricity received from external sources such as KEPCO. ESS stands for Energy Storage System, and xEMS refers to a system that measures and controls a facility’s energy usage. MW denotes power capacity, while kWh and MWh represent the amount of energy consumed over a specific period. PUE is an efficiency metric calculated by dividing the facility’s total energy consumption by its IT energy consumption.

Do I need to sign a contract with the construction company first?

In practice, the first step is to select a design firm to review the architecture, site location, and power demand, and to confirm the necessary evaluations and supply conditions. The construction contractor should be selected before entrusting tasks such as formal application submission, cost estimates, and construction; however, it is not necessary to finalize a contract for all construction work from the outset.

Are the KEPCO technical review, the power system impact assessment, and the Ministry of Climate Change review the same thing?

The KEPCO technical review is a stage in which technical data on the power grid is provided. The company preparing the power system impact assessment and the project owner use this response and supporting project documentation to finalize the assessment report, submit it to the Ministry of Climate, and receive the results of the policy evaluation and deliberation. All submission and result documents must be retained.

Does completing the power system impact assessment also mean that the energy usage plan consultation is finished?

No. The criteria, review items, and required documentation differ between the power system impact assessment and the energy usage plan consultation. Verify the applicability of each, use the same design input values, but manage the submissions and results separately.

If I sign a contract with a power system impact assessment provider, does that also serve as a contract with KEPCO?

No. A contractor agreement is a contract to handle data preparation and application support, whereas a KEPCO electricity service contract is a power supply contract between the applicant and KEPCO. It is important to distinguish between the authority to submit applications on behalf of others and the party that is the ultimate contracting entity.

If I include PPAs or emergency generators in the Ministry of Climate Change’s evaluation, will I receive bonus points?

November 28, 2025: For the pilot operation, PPA power demand and emergency generators are excluded from the calculation of on-site power generation capacity. Renewable energy, energy efficiency measures, and energy storage systems (ESS) must also be separately verified to ensure they comply with the applicable requirements and standards for installation, operation, and implementation.

Does commercial operation begin immediately after receiving a building permit or passing the pre-operation inspection?

We verify compliance with relevant inspections—such as building occupancy permits, pre-service electrical inspections, and fire safety inspections—as well as the commencement of power supply by KEPCO. Following this, we determine when to begin commercial operation after ensuring alignment with operator acceptance criteria, integrated commissioning, and the safety management system.

How long should the total duration be, and what should the estimated cost be?

It varies depending on the site, scope of evaluation, design maturity, grid reinforcement, equipment delivery schedules, and supplementary measures. The agency’s review period is not presented as the total development period; instead, costs—including KEPCO’s review fees, contractor service fees, facility contribution fees, and construction costs—are calculated separately, along with schedules for each prerequisite condition.

Now it’s time to determine the order of my business sites.

Please prepare the address, target IT capacity, planned start date, and any responses or permits you have received from KEPCO. We will organize the necessary reviews and assign responsibilities based on the information provided.

Free Address Analysis →Consultation on Progress by Project Site →Detailed Guide to Power Connections →

IDC Definition, Data Center Sites, and Power Documentation Guide →

SOURCE NOTES / 2026.09.24

Official Basis and Effective Date

We have distinguished between operational guidelines and draft regulations.

The explanation of the documents and submission process for the Grid Impact Assessment is based on the November 28, 2025, notice regarding changes to the pilot operation and the attached application form. Notice No. 2026-673 was confirmed to be a draft administrative notice and was therefore not applied as a final regulation. You must verify whether the final notice has taken effect and check the latest forms and submission locations before actually submitting an application. The scope of the company’s contract and the phased handover checklist are provided in the AI-DC Practical Guide, which reorganizes this information to suit the project owner’s operations.

  1. [1]
    Ministry of Climate, Energy, and Environment · Notice Regarding Changes to the Pilot Operation of the Power System Impact Assessment (November 28, 2025) ↗

    Attachment Procedure Guide: Scope, Submission Order, Technical/Non-Technical/Policy Review, Costs, and Implementation Verification. Use the reference date indicated in the pilot operation document.

  2. [2]
    Enforcement Decree of the Distributed Energy Act, Article 28 · Timing for Submission of Evaluation Reports ↗

    Verify the provisions effective September 18, 2026. Submit the assessment report at least three months prior to applying for approval of eligible projects.

  3. [3]
    Attachment to the Ministry of Climate Change’s Notice · KEPCO Technical Review Application Form ↗

    Applicant, power consumption overview, current status, documents received for scheduled notifications, business registration certificate, etc. This is an attachment to the November 28, 2025, announcement; please reconfirm the latest submission forms.

  4. [4]
    Korea Electric Power Corporation ON · Electricity Service Application ↗

    Verify the current application forms, required documents, and the competent office for formal new applications. Categorize changes and expansions under the appropriate application menu.

  5. [5]
    Korea Energy Agency · Consultation on Energy Usage Plans ↗

    Standards by private and public facilities/projects; procedures for submission to the Ministry of Climate, review by the Industrial Complex Corporation, consultation, implementation, and post-implementation management.

  6. [6]
    Korea Electrical Safety Corporation · Electrical Safety Here ↗

    Check the relevant services—such as construction plans for private electrical facilities and pre-operation inspections—as well as the application forms and required documents.

  7. [7]
    Article 11 of the Electrical Construction Business Act · Separate Bidding ↗

    Verify the principles and exceptions for separate bidding for electrical construction projects.

  8. [8]
    Article 14-3 of the Power Technology Management Act · Separate Contracting for Design and Supervision ↗

    Confirm whether separate bids are issued for the design and construction supervision services for the relevant power facilities and identify any exceptions.

  9. [9]
    National Law Information Center · Building Act ↗

    Building permits, construction commencement, occupancy permits, and consultations regarding relevant laws and regulations. Verify individual ordinances and project conditions as well.

  10. [10]
    Ministry of Climate No. 2026-673 · Administrative Notice on the Draft Operating Regulations for the Power System Impact Assessment ↗

    Draft administrative notice. Do not consider this to be a scoring system that has been finalized, officially announced, or currently in effect.

  11. [11]
    National Law Information Center · Enforcement Decree of the Energy Rationalization Act ↗

    Verify the applicable provisions for each project, including who is subject to energy use plan consultations and the deadlines for drafting and submitting such plans.

  12. [12]
    Act on the Planning and Use of National Land ↗

    Standards related to land use zones and development activities. Check additional laws and regulations governing individual land types, such as farmland and mountainous land.

  13. [13]
    Environmental Impact Assessment Act ↗

    Verify the types of environmental assessments and consultation processes based on the project and location.

  14. [14]
    Air Quality Conservation Act ↗

    Verify the applicability of permits and licenses for relevant emission facilities, such as power generation facilities. Separate jurisdictional standards apply to water use and noise.

  15. [15]
    Act on Countermeasures Against Natural Disasters ↗

    Confirm consultation with relevant parties, such as those subject to environmental impact assessments.

  16. [16]
    Special Act on Underground Safety Management ↗

    Verify underground safety assessments and management in accordance with excavation and project conditions.

  17. [17]
    Act on the Promotion of Urban Transportation Improvement ↗

    Scope and consultation for traffic impact assessments. Check regional ordinances as well.

  18. [18]
    Road Act ↗

    Review matters such as the use of roads for access and exit routes.

  19. [19]
    Fire Protection Facilities Construction Business Act ↗

    Verify fire safety design, construction, and supervision, as well as the reporting and inspection of the relevant construction projects.

  20. [20]
    Information and Communications Construction Business Act ↗

    Verify relevant obligations, such as information and communications construction, supervision, and pre-service inspections.

  21. [21]
    Korea Energy Agency · Energy Conservation Plan ↗

    Verify the Building Energy Conservation Plan system. Distinguish it from consultations on energy usage plans.

  22. [22]
    Special Act on the Promotion of Distributed Energy ↗

    Verify the standards regarding the scope, implementation, modification, and succession of distributed energy facilities and power system impact assessments.

Start a consultation · Choose a channel