KOREA DATA CENTER POWER CONNECTION

Data center electricity, power, and substations,
Distinguish between applications and secured capacity.

We review the process in the order that actual documents change—from calculating electrical equipment and power requirements to identifying candidate nearby substations, submitting applications to KEPCO, supply negotiations, grid connection, grid impact assessment, service connection design, and the start of power supply.
Key Principles

The distance to a substation, receipt of an electricity service application, supply negotiations, contracted power, and the actual start of supply do not have the same meaning. AI-DC KOREA separates the names, reference dates, parties involved, capacities, and desired start dates from verified documents and does not present unverified supply possibilities as confirmed values.

If you’re wondering which companies to contract with or what documents are required,

Preparatory Documents for KEPCO Technical Review, Power System Impact Assessment, and Energy ConsultationWow Contract Timing and Scope by CompanyPlease refer to the comprehensive licensing guide. Apply the evaluation to the target project from the six steps below, and verify the sequence and parallel schedules for each project.

POWER TERMS

The Difference Between Data Centers, Electrical Systems, Power Systems, and Substations

Do not use the terms “facility,” “required capacity,” and “grid connection candidate” interchangeably.
01

Data Center Electricity

This refers to the power distribution system, including power receiving equipment, transformers, power distribution panels, UPS systems, emergency generators, grounding and protective relays, and the data hall. We review not only equipment capacity but also single-circuit wiring, redundancy, selective coordination, and test plans.

02

Data Center Power

IT load, total facility load, PUE, contracted power, requested power, actual available capacity, and the timing of supply are all distinct values. It is important to distinguish between calculated values and official responses from KEPCO.

03

Data Center Substation

Substations located near the project site are potential connection points. Actual power supply capacity will be finalized after reviewing voltage, available capacity, the withdrawal bay, the connecting grid, reinforcement work, the transmission line route, and the supply schedule.

01POWER CONNECTION STAGE

Summary of Load and Business Plans

We will coordinate with the electrical design firm to finalize the target IT load, total facility load, active and reserve configurations, as well as the initial, final, and expansion capacities and dates of use.

02POWER CONNECTION STAGE

Confirmation of Projects Subject to Advance Notice and Assessment

A preliminary notice is issued once the applicant, site justification, and power supply plan are in place. Eligibility for the power system impact assessment and the energy usage plan consultation is determined based on different criteria.

03POWER CONNECTION STAGE

Separate application required for KEPCO technical review

For projects subject to the power system impact assessment, a separate application for technical review must be submitted along with the notice of intent, application form, business registration certificate, and other required documents. Respond to KEPCO’s guidance on costs and corrective measures, and await the results of the technical review.

04POWER CONNECTION STAGE

Prepared by the Ministry of Climate and Energy and submitted to the Ministry of Climate and Energy

Based on KEPCO’s response, the project operator prepares an evaluation report that includes supporting documentation for business, financial, employment, and efficiency plans, and submits it to the Ministry of Climate Change. The project operator manages both the statutory submission deadlines prior to project approval and the schedule for energy consultations in parallel.

05POWER CONNECTION STAGE

Official Application, Supply Conditions, and Contract

Based on the assessment results and project conditions, we proceed with the formal application for electricity use, finalize the supply plan, discuss charges and construction boundaries, and enter into an electricity service contract. Even for projects not subject to the power system impact assessment, a review by KEPCO and a contract are required.

06POWER CONNECTION STAGE

Design, Construction, Inspection, and Transmission

We proceed with detailed design, construction, and the relevant pre-operation inspection in accordance with the permit conditions. We verify the conditions for the commencement of power supply by KEPCO, building occupancy approval, and integrated commissioning and handover for operations, respectively.

DOCUMENT CONTROL

Scope of Documentation

Instead of using the single term “power supply,” each document should record both the facts that have been verified and those that have not yet been verified.
01

Application for Electricity Service Accepted

Verification: The fact that an application has been received

Category: This does not represent a determination of available capacity or timing.

02

Response to Supply Review and Consultation

Verification: Connection systems, conditions, and additional data as of the review date

Category: Distinguish from electricity service contracts and project completion

03

Electricity Service Agreement

Verification: Contract Power, Supply Conditions, and Parties

Category: This does not constitute a building permit or commercial operation.

04

Design of Power Lines and Power Receiving Equipment

Verification: Feeder Path, Equipment Scope, and Protection Methods

Category: Land use, road occupancy, and construction permits must be verified separately.

05

Results of the Power System Impact Assessment

Verification: Statutory Scope and Conditions of Assessment

Category: Distinction from the completion of individual supply projects by KEPCO

06

Basis for Supply Commencement and Metering

Verification: Stages of Actual Electricity Availability

Category: Distinguish from commercial operation of IT equipment and SLAs

INPUT CHECKLIST

Materials to Prepare Before Review

01

Project site address and lot number; basis for land ownership or usage rights

02

Target IT Load, PUE, Facility Load, Contracted Power, and Phased Expansion Plans

03

Desired supply voltage, service commencement date, and testing and commercial operation schedules

04

Current Status of Construction, Development Activities, Roads, Utility Right-of-Way Routes, and Telecommunications Connections

05

Single-line diagrams, configurations of transformers, UPS systems, and generators, and locations of power receiving equipment

06

Documents regarding existing KEPCO case numbers, responses, contracts, fees, and scope of work

OFFICIAL EVIDENCE

Official source text and actual platform features

Procedure guide updated on September 24, 2026. Please verify laws, regulations, terms and conditions, and agency procedures again on the actual application date.
04

National Law Information Center · Enforcement Decree of the Special Act on the Promotion of Distributed Energy

Official source text →
05

Ministry of Climate, Energy, and Environment · Notice Regarding Changes to the Pilot Operation of the Power System Impact Assessment (November 28, 2025)

Official source text →

FREQUENT QUESTIONS

Data Center Electricity, Power, and Substation FAQ

01

What types of equipment are included in data center electricity consumption?

This includes everything from the KEPCO power supply point to transformers, power distribution panels, UPS systems, batteries, emergency generators, STS/PDUs, data hall power distribution, grounding, protective relays, metering, and monitoring equipment. The facility configuration must be designed to meet the target availability and phased IT load requirements.

02

Is data center power consumption the same as IT load?

No. IT load refers to the load from IT equipment such as servers, while the total power requirement for a data center is the sum of facility loads, including cooling, electrical, mechanical, and lighting. The requested power is calculated separately, taking into account PUE, power factor, reserve margin, and phased expansion plans.

03

How are data center substations selected?

After identifying candidate substations with a voltage of 154 kV or higher based on location, we verify their operational status, whether they are used for railways, the connected power grid, availability of spare capacity and withdrawal potential, as well as the feed-in route and supply schedule using documents provided by KEPCO. The preferred substation is not determined solely based on proximity.

04

If there is a nearby substation, is it possible to connect the data center to the power grid?

No. Distance is a site selection indicator. You must confirm the following via an official response from KEPCO: substation capacity, grid connection, transmission line route, reinforcement work, supply schedule, and the results of the grid review.

05

Are the IT load and the capacity requested from KEPCO the same?

They are not the same. The applied capacity is reviewed separately, taking into account IT loads, facility loads (such as cooling, electricity, mechanical systems, and lighting), as well as PUE, power factor, reserve ratio, and phased expansion plans.

06

What does “data center power capacity” mean?

This refers to the total power capacity reviewed and contracted for a facility to receive from the power grid. It is not the same as the IT load; rather, it reflects the facility load calculated using PUE, demand factor, power factor, reserve configuration, and phased expansion. The requested capacity, contracted power, and actual available capacity must be distinguished at each stage of the documentation.

07

Does submitting an application for electricity service mean that power supply has been secured?

No. Application submission, supply review, electricity service agreement, design and construction, safety inspection, and commencement of supply are all distinct stages.

08

Is a facility subject to a power system impact assessment if it is 10 MW or more?

The current Enforcement Decree of the Distributed Energy Act sets the threshold at electricity usage contracts of 10 MW or more. However, details regarding location, expansion, business type, and any special provisions currently in effect must be verified individually with the relevant authorities based on the latest laws and regulations.

09

Can power connection costs be calculated based on the distance to the substation?

It cannot be calculated based on distance alone. Factors such as supply voltage, overhead and underground sections, road and river crossings, land use, substations and switching equipment, grid reinforcement, and the scope of construction responsibility must be taken into account.

10

What can I check for free on AI-DC KOREA?

You can check the public maps, centers, permits, and technical database, as well as the review items in this guide. Assessments of supply feasibility, routes, costs, and schedules for individual sites will be conducted separately after receiving the address and official documents.

From Free Check to Individual Review

After identifying candidates using publicly available data, submit the address, requested capacity, desired start date, and KEPCO documents; we will then identify any missing information and the next verifying agency.

Free Data Center Site Analysis →Database based on power and equipment standards →Permit and Licensing Procedures →Submit Power Review Request →

Information on IDC, Racks, and Power System Impact Assessment Reports →

Scope of Assessment

This page is a public guide explaining the application and consultation process. It does not guarantee the available capacity, schedule, route, cost, or evaluation results for specific project sites; the latest official documents from Korea Electric Power Corporation (KEPCO) and relevant agencies serve as the final authority.