01What types of equipment are included in data center electricity consumption?
This includes everything from the KEPCO power supply point to transformers, power distribution panels, UPS systems, batteries, emergency generators, STS/PDUs, data hall power distribution, grounding, protective relays, metering, and monitoring equipment. The facility configuration must be designed to meet the target availability and phased IT load requirements.
02Is data center power consumption the same as IT load?
No. IT load refers to the load from IT equipment such as servers, while the total power requirement for a data center is the sum of facility loads, including cooling, electrical, mechanical, and lighting. The requested power is calculated separately, taking into account PUE, power factor, reserve margin, and phased expansion plans.
03How are data center substations selected?
After identifying candidate substations with a voltage of 154 kV or higher based on location, we verify their operational status, whether they are used for railways, the connected power grid, availability of spare capacity and withdrawal potential, as well as the feed-in route and supply schedule using documents provided by KEPCO. The preferred substation is not determined solely based on proximity.
04If there is a nearby substation, is it possible to connect the data center to the power grid?
No. Distance is a site selection indicator. You must confirm the following via an official response from KEPCO: substation capacity, grid connection, transmission line route, reinforcement work, supply schedule, and the results of the grid review.
05Are the IT load and the capacity requested from KEPCO the same?
They are not the same. The applied capacity is reviewed separately, taking into account IT loads, facility loads (such as cooling, electricity, mechanical systems, and lighting), as well as PUE, power factor, reserve ratio, and phased expansion plans.
06What does “data center power capacity” mean?
This refers to the total power capacity reviewed and contracted for a facility to receive from the power grid. It is not the same as the IT load; rather, it reflects the facility load calculated using PUE, demand factor, power factor, reserve configuration, and phased expansion. The requested capacity, contracted power, and actual available capacity must be distinguished at each stage of the documentation.
07Does submitting an application for electricity service mean that power supply has been secured?
No. Application submission, supply review, electricity service agreement, design and construction, safety inspection, and commencement of supply are all distinct stages.
08Is a facility subject to a power system impact assessment if it is 10 MW or more?
The current Enforcement Decree of the Distributed Energy Act sets the threshold at electricity usage contracts of 10 MW or more. However, details regarding location, expansion, business type, and any special provisions currently in effect must be verified individually with the relevant authorities based on the latest laws and regulations.
09Can power connection costs be calculated based on the distance to the substation?
It cannot be calculated based on distance alone. Factors such as supply voltage, overhead and underground sections, road and river crossings, land use, substations and switching equipment, grid reinforcement, and the scope of construction responsibility must be taken into account.
10What can I check for free on AI-DC KOREA?
You can check the public maps, centers, permits, and technical database, as well as the review items in this guide. Assessments of supply feasibility, routes, costs, and schedules for individual sites will be conducted separately after receiving the address and official documents.