Nebius Independence Missouri campus
data center project · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| planned_facility_capacity_unspecified | 1200 MW | publisher total plan · Campus · Plan As-of date Not stated Sources EV-b5e91a41c616301ba4631257 |
| planned_utility_power | 800 MW | Independence Power and Light proposal · Campus · Plan As-of date Not stated Sources EV-b5e91a41c616301ba4631257 |
| planned_onsite_generation | 400 MW | onsite generation plan · Campus · Plan As-of date Not stated Sources EV-b5e91a41c616301ba4631257 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| source_record_id | nebius-independence |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source Not stated · Retrieved 2026-10-05
nebius.com
Source location article body
Sources EV-b5e91a41c616301ba4631257Evidence SHA-256 03d3058b108279389f683dadb67a4fea4b6d02babd1ad75e0cb37278ca1305a8 · raw_http_response