Warsaw 2 Energy Storage / WBA2
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 11 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-0d172c37b40f9b4654f90c6a |
| Net Summer Capacity (MW) | 10.1 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-0d172c37b40f9b4654f90c6a |
| Net Winter Capacity (MW) | 10.1 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-0d172c37b40f9b4654f90c6a |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 3046 |
| Entity Name | Duke Energy Progress - (NC) |
| Plant ID | 69988 |
| Plant Name | Warsaw 2 Energy Storage |
| Google Map | Map |
| Bing Map | Map |
| Plant State | NC |
| County | Duplin |
| Balancing Authority Code | CPLE |
| Sector | Electric Utility |
| Generator ID | WBA2 |
| Nameplate Capacity (MW) | 11 |
| Net Summer Capacity (MW) | 10.1 |
| Net Winter Capacity (MW) | 10.1 |
| Technology | Batteries |
| Energy Source Code | MWH |
| Prime Mover Code | BA |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (V) Under construction, more than 50 percent complete |
| Latitude | 35.003702 |
| Longitude | -78.1165 |
| Original text | (V) Under construction, more than 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:153 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:2510
Sources EV-971bb086427d22266658ca4cEvidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 d8c8400dfc8d645fac5ca6cd3d3cccc1689259ee374110801cfbf22efc594e59
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:153
Sources EV-0d172c37b40f9b4654f90c6aEvidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 04b95f98adb6c941d049d864039a46caf917c1f6c9bed56d946c994fadbbb7a8
Usage terms US government public domain