| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 2.4 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-110d7b63cbb07ab8b9fdd939 |
| Net Summer Capacity (MW) | 2.4 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-110d7b63cbb07ab8b9fdd939 |
| Net Winter Capacity (MW) | 2.4 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-110d7b63cbb07ab8b9fdd939 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 65539 |
| Entity Name | Pivot Energy |
| Plant ID | 69052 |
| Plant Name | MDD109-NCBP BLDG 11-Manekin |
| Google Map | Map |
| Bing Map | Map |
| Plant State | MD |
| County | Prince Georges |
| Balancing Authority Code | PJM |
| Sector | IPP Non-CHP |
| Generator ID | MD11 |
| Nameplate Capacity (MW) | 2.4 |
| Net Summer Capacity (MW) | 2.4 |
| Net Winter Capacity (MW) | 2.4 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (V) Under construction, more than 50 percent complete |
| Latitude | 38.8739 |
| Longitude | -76.7342 |
| Original text | (V) Under construction, more than 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:102 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:1627
Sources EV-39f8b88e6f6fab644ac4876eEvidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 7a40ea79600649fa0ac8a6223d169a5861c4ac43df5f770cd6837045b7c835b9
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:102
Sources EV-110d7b63cbb07ab8b9fdd939Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 1b04075b6aa709eed0522d8fd74edec43c6ab1983e667592e76d3b12d75f93ef
Usage terms US government public domain