Eagle Springs Hybrid / EGSB
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 55.1 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-b5042aacd9ab8ea244184640 |
| Net Summer Capacity (MW) | 55.1 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-b5042aacd9ab8ea244184640 |
| Net Winter Capacity (MW) | 55.1 MW | Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-b5042aacd9ab8ea244184640 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 65815 |
| Entity Name | Sunraycer Assets I LLC |
| Plant ID | 66341 |
| Plant Name | Eagle Springs Hybrid |
| Google Map | Map |
| Bing Map | Map |
| Plant State | TX |
| County | Delta |
| Balancing Authority Code | ERCO |
| Sector | IPP Non-CHP |
| Generator ID | EGSB |
| Nameplate Capacity (MW) | 55.1 |
| Net Summer Capacity (MW) | 55.1 |
| Net Winter Capacity (MW) | 55.1 |
| Technology | Batteries |
| Energy Source Code | MWH |
| Prime Mover Code | BA |
| Planned Operation Month | 12 |
| Planned Operation Year | 2026 |
| Status | (V) Under construction, more than 50 percent complete |
| Latitude | 33.433264 |
| Longitude | -95.57444 |
| Original text | (V) Under construction, more than 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:464 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:618
Sources EV-dbaef53bd96790b34614c70bEvidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 030c7998cfdb54c5f355c8a406dd01dca1f0ae97b3d195897aa93ec699d381d0
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:464
Sources EV-b5042aacd9ab8ea244184640Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 18a25c1fdd9da45a936201007e5c8c91975b5260cdb26caebfc1406ad61291df
Usage terms US government public domain