Mark Center Solar Project / MRC1
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 90 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-01acd56d863c0c8eaec8c0ac |
| Net Summer Capacity (MW) | 90 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-01acd56d863c0c8eaec8c0ac |
| Net Winter Capacity (MW) | 90 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-01acd56d863c0c8eaec8c0ac |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 67786 |
| Entity Name | Naturgy Solar Operation USA LLC |
| Plant ID | 65050 |
| Plant Name | Mark Center Solar Project |
| Google Map | Map |
| Bing Map | Map |
| Plant State | OH |
| County | Defiance |
| Balancing Authority Code | PJM |
| Sector | IPP Non-CHP |
| Generator ID | MRC1 |
| Nameplate Capacity (MW) | 90 |
| Net Summer Capacity (MW) | 90 |
| Net Winter Capacity (MW) | 90 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 41.288044 |
| Longitude | -84.61132 |
| Original text | (U) Under construction, less than or equal to 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:31 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:489
Sources EV-d14efb4dbdf24159528362a0Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 388da1028eac2b1e5628963609fc7d73d79509d7be20129a772dc1ae28ca2b48
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:31
Sources EV-01acd56d863c0c8eaec8c0acEvidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 0239348941ade10769dd16dfd943ea2fb7e35c74531c994e852f60a42d9b36a5
Usage terms US government public domain