Mark Center Solar Project / MRC1
발전기 · 계획
| 지표·조건 | 출처 값 | 기준·범위·단계 |
|---|---|---|
| Nameplate Capacity (MW) | 90 MW | 원출처 열 정의 · 발전기 · (U) Under construction, less than or equal to 50 percent complete 기준일 2026-08 근거 EV-01acd56d863c0c8eaec8c0ac |
| Net Summer Capacity (MW) | 90 MW | 원출처 열 정의 · 발전기 · (U) Under construction, less than or equal to 50 percent complete 기준일 2026-08 근거 EV-01acd56d863c0c8eaec8c0ac |
| Net Winter Capacity (MW) | 90 MW | 원출처 열 정의 · 발전기 · (U) Under construction, less than or equal to 50 percent complete 기준일 2026-08 근거 EV-01acd56d863c0c8eaec8c0ac |
원출처 세부 필드
| 원출처 항목 | 공개값·조건 |
|---|---|
| Entity ID | 67786 |
| Entity Name | Naturgy Solar Operation USA LLC |
| Plant ID | 65050 |
| Plant Name | Mark Center Solar Project |
| Google Map | Map |
| Bing Map | Map |
| Plant State | OH |
| County | Defiance |
| Balancing Authority Code | PJM |
| Sector | IPP Non-CHP |
| Generator ID | MRC1 |
| Nameplate Capacity (MW) | 90 |
| Net Summer Capacity (MW) | 90 |
| Net Winter Capacity (MW) | 90 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 41.288044 |
| Longitude | -84.61132 |
| 원문 상태 | (U) Under construction, less than or equal to 50 percent complete |
| 좌표 정확도 | source_precision_not_independently_surveyed |
| source_record_id | Planned:31 |
Coordinates locate the plant, including when this record describes one generator.
위치: 발전소 위치 · 발전기 개별 위치 아님
원문·기준일·확인일 2건
자료 기준 2025 · 수집 확인 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
원문 위치 3_1_Generator_Y2025.xlsx#Proposed:489
근거 EV-d14efb4dbdf24159528362a0자료 SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 388da1028eac2b1e5628963609fc7d73d79509d7be20129a772dc1ae28ca2b48
자료 기준 2026-08 · 수집 확인 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
원문 위치 Planned:31
근거 EV-01acd56d863c0c8eaec8c0ac자료 SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 0239348941ade10769dd16dfd943ea2fb7e35c74531c994e852f60a42d9b36a5