Cumberland (TN) / CTG1
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 454.8 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c77b094d75d4b8cdeab7808b |
| Net Summer Capacity (MW) | 372.9 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c77b094d75d4b8cdeab7808b |
| Net Winter Capacity (MW) | 409.3 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c77b094d75d4b8cdeab7808b |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 18642 |
| Entity Name | Tennessee Valley Authority |
| Plant ID | 3399 |
| Plant Name | Cumberland (TN) |
| Google Map | Map |
| Bing Map | Map |
| Plant State | TN |
| County | Stewart |
| Balancing Authority Code | TVA |
| Sector | Electric Utility |
| Generator ID | CTG1 |
| Unit Code | 1 |
| Nameplate Capacity (MW) | 454.8 |
| Net Summer Capacity (MW) | 372.9 |
| Net Winter Capacity (MW) | 409.3 |
| Technology | Natural Gas Fired Combined Cycle |
| Energy Source Code | NG |
| Prime Mover Code | CT |
| Planned Operation Month | 12 |
| Planned Operation Year | 2034 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 36.3903 |
| Longitude | -87.6539 |
| Original text | (U) Under construction, less than or equal to 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:2311 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:71
Sources EV-a9f4765271619b6ce1888aecEvidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 99152143c64cb2ad99e148fa88daffb743ea90fe1b44792f99dd80dd5c7a2edd
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:2311
Sources EV-c77b094d75d4b8cdeab7808bEvidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 ffd8629319261ee0aed346c667b47fedff5fe0a91be0b4a90c43f1b011ec3ff1
Usage terms US government public domain