POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 18items · current page 1–18 · Source records, not unique facilities.
Metric or condition Source value Basis, scope and stage project_name_voltage_label 154 kV literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-bdf43c29e529bfadbb5611b7
Detailed source fields Original source field Published value or condition stable_project_id kproj_fad87c7018753b8d stable_project_key prjtDef:231339:ESB project_definition 231339 first_region_code ESB manual_source_format false project_name 154kV 사등S/S 건설사업 project_name_list 154kV 사등S/S 건설사업 purpose 거제 서부권 개발지역 부하 공급 project_region_detail 경상남도 거제시 project_period_raw 2013.06~2031.06 project_scale_raw 154KV M.TR(45/60MVA) * 2BANK responsible_office_raw 남부건설본부/직할 equipment_type 변전 headquarters 남부건설본부 office 직할 current_stage_raw 계획확정-사업승인전 snapshot_count 1 active_snapshot_count 1 snapshot_ids first_seen_at 2026-10-02 last_confirmed_at 2026-10-02T01:55:13Z location_precision region_only geometry_semantics no_verified_geometry geometry Not obtained source_list_url https://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do source_detail_url https://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do Original text 계획확정-사업승인전 source_record_id stable_project_id:kproj_fad87c7018753b8d
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location stable_project_id:kproj_fad87c7018753b8d
Sources EV-bdf43c29e529bfadbb5611b7 Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba 행 SHA-256 54d7822dc67020abf1fec66a334502b49545e3b17e05aa6a6a17b2faac5b6c27 Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2026-02 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2025-07 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type design_completion date 2029-09 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2027-03 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2025-07 date_precision month assertion source_stated_candidate verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type route_or_site_confirmation date 2026-04 date_precision month assertion source_stated_candidate verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type route_or_site_confirmation date 2026-09 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type construction_completion date 2031-06 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2024-05 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type project_period_start date 2013-06 date_precision month assertion source_project_period verification_status source_field operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type project_period_end date 2031-06 date_precision month assertion source_project_period verification_status source_field operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2026-04 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2026-04 date_precision month assertion source_mentioned_unverified verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type source_mentioned_date date 2029-09 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition event_type construction_start date 2030-03 date_precision month assertion planned verification_status source_text_candidate operational_proof false source_key 202609|231339|ESB migration_status reused_from_validated_revision1_schedule
No separate metric summary is available. Consult the detailed source fields.
Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition snapshot_id ksnap_e8b9d1a6f1774344 stable_project_id kproj_fad87c7018753b8d source_key 202609|231339|ESB basic_ym 202609 source_stage_raw 계획확정-사업승인전 project_name_list 154kV 사등S/S 건설사업 project_name_detail 154kV 사등S/S 건설사업 region_summary_raw 경상남도 거제시등 1 지역 equipment_type_raw 변전 headquarters_raw 남부건설본부 office_raw 직할 section_fields 사업 규모 154KV M.TR(45/60MVA) * 2BANK 입지선정 전력입지영향평가 용역 착수: 2025.07 입지선정위원회 구성시기: 2026.04 참여 위원 수 : 16 경과지(부지) 확정: 주민의견 수렴 지자체 공고 열람: 설명회·공청회: 자체설명회: [진행경과] □ '24.05 : 산단 취소에 따른 관련부서 업무협의 □ '25.07 : 전력영향평가 용역발주 □ '26.02 : 입지선정위원회 구성완료 □ '26.04 : 입지선정위원회 1,2차 회의 시행 [향후계획] □ '26.09 : 변전소 입지 및 송전선로 경과지 확정 □ '27.03 : 전원개발사업 실시계획 신청 □ '29.09 : 용지매수 완료 □ '29.09 : 변전 실시설계 완료 □ '30.03 : 변전공사 착공 □ '31.06 : 변전공사 준공 future_plan_redacted □ 향후계획 [진행경과] □ '24.05 : 산단 취소에 따른 관련부서 업무협의 □ '25.07 : 전력영향평가 용역발주 □ '26.02 : 입지선정위원회 구성완료 □ '26.04 : 입지선정위원회 1,2차 회의 시행 [향후계획] □ '26.09 : 변전소 입지 및 송전선로 경과지 확정 □ '27.03 : 전원개발사업 실시계획 신청 □ '29.09 : 용지매수 완료 □ '29.09 : 변전 실시설계 완료 □ '30.03 : 변전공사 착공 □ '31.06 : 변전공사 준공 attachment_count 0 source_detail_sha256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 first_seen_at 2026-10-02 last_confirmed_at 2026-10-02T01:55:13Z Original reference period 202609 source_record_id 202609|231339|ESB
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location snapshot_id:ksnap_e8b9d1a6f1774344
Sources EV-c99c6b4d93e1cbc2138a9cc0 Evidence SHA-256 eb438a6c46634d9147f761f6f822a80f30b33e104ec7af501993469d03bb1f84 행 SHA-256 6a28bd88917c4b07740380c7a2a3e512e0bd55f6c88458304fce2169d6499c8f Observations for this power asset History for this project Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition stable_project_id kproj_fad87c7018753b8d stable_project_key prjtDef:231339:ESB project_definition 231339 first_region_code ESB manual_source_format false project_name 154kV 사등S/S 건설사업 project_name_list 154kV 사등S/S 건설사업 purpose 거제 서부권 개발지역 부하 공급 project_region_detail 경상남도 거제시 project_period_raw 2013.06~2031.06 project_scale_raw 154KV M.TR(45/60MVA) * 2BANK responsible_office_raw 남부건설본부/직할 equipment_type 변전 headquarters 남부건설본부 office 직할 current_stage_raw 계획확정-사업승인전 snapshot_count 1 active_snapshot_count 1 snapshot_ids first_seen_at 2026-10-02 last_confirmed_at 2026-10-02T01:55:13Z location_precision region_only geometry_semantics no_verified_geometry geometry Not obtained source_list_url https://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do source_detail_url https://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do Original text 계획확정-사업승인전 source_record_id stable_project_id:kproj_fad87c7018753b8d
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items kepco_planned ↗ Data Source 2026-09 · Retrieved 2026-10-02
한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분
Source location stable_project_id:kproj_fad87c7018753b8d
Sources EV-bdf43c29e529bfadbb5611b7 Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba 행 SHA-256 54d7822dc67020abf1fec66a334502b49545e3b17e05aa6a6a17b2faac5b6c27 Observations for this power asset History for this project