POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 5items · current page 1–5 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 광석(물왕)S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-eab8001f13ba914cbeb0a08d
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_8b9d96c0e45f45f7
stable_project_keyprjtDef:231302:ESB
project_definition231302
first_region_codeESB
manual_source_formatfalse
project_name154kV 광석(물왕)S/S 건설사업
project_name_list154kV 광석S/S 건설사업
purpose시흥시 장현,목감택지개발지구내 전력공급
project_region_detail경기도 시흥시
project_period_raw2017.01~2027.12
project_scale_raw154KV MTR 60MVA×2BANK, 170KV GIS×10CCT
responsible_office_raw경인건설본부/남서울인천건설지사
equipment_type변전
headquarters경인건설본부
office남서울인천건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_152c962a53f5f57b
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_8b9d96c0e45f45f7

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_8b9d96c0e45f45f7

Sources EV-eab8001f13ba914cbeb0a08d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 2fb4a3eaef3a4c061a023976f378bd5c4865f4d70b167ef628420ab54c3c8419
Source schedule candidates · KOR · kepco_planned

154kV 광석(물왕)S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2027-12
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231302|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_152c962a53f5f57b

Sources EV-9c62393f18d4121cd7a89819
Evidence SHA-256 f89c193baf228f2d17ddc1922a274204e49fe0c5bbb077cd1d21de3b1e61dc95
행 SHA-256 4d9d69b6603f1dc0fe47b2cb34fc6cd7f352b5b2be08ce4885341f5cec39e44d
Source schedule candidates · KOR · kepco_planned

154kV 광석(물왕)S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2017-01
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231302|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_152c962a53f5f57b

Sources EV-9c62393f18d4121cd7a89819
Evidence SHA-256 f89c193baf228f2d17ddc1922a274204e49fe0c5bbb077cd1d21de3b1e61dc95
행 SHA-256 4d9d69b6603f1dc0fe47b2cb34fc6cd7f352b5b2be08ce4885341f5cec39e44d
Source snapshots by date · KOR · kepco_planned

154kV 광석(물왕)S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_152c962a53f5f57b
stable_project_idkproj_8b9d96c0e45f45f7
source_key202609|231302|ESB
basic_ym202609
source_stage_raw사업승인-공사착수전
project_name_list154kV 광석S/S 건설사업
project_name_detail154kV 광석(물왕)S/S 건설사업
region_summary_raw경기도 시흥시등 1 지역
equipment_type_raw변전
headquarters_raw경인건설본부
office_raw남서울인천건설지사
section_fields
Project purpose
  • 시흥시 장현,목감택지개발지구내 전력공급
Project region
  • 경기도 시흥시
Project period
  • 2017.01~2027.12
사업 규모
  • 154KV MTR 60MVA×2BANK, 170KV GIS×10CCT
담당 사업소
  • 경인건설본부/남서울인천건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
전원개발사업 실시계획 승인
사업설계
  • 설계용역: 기본설계: 2024.01 ~ 2024.07 실시설계: 설계담당자: [redacted]
○'17.04 : 시흥장현 택지지구 변경협의요청(국토부→관련기관) ○'17.05 : 시흥장현 택지지구 협의완료(국토부) ○'17.06 : 실시계획 승인(국토부제2017-381호) ○'17.12 : 토지매매계약 ○'26.10 : 공사착공 ○'28.09 : 준공
future_plan_redacted□ 향후계획 ○'17.04 : 시흥장현 택지지구 변경협의요청(국토부→관련기관) ○'17.05 : 시흥장현 택지지구 협의완료(국토부) ○'17.06 : 실시계획 승인(국토부제2017-381호) ○'17.12 : 토지매매계약 ○'26.10 : 공사착공 ○'28.09 : 준공
attachment_count0
source_detail_sha256f89c193baf228f2d17ddc1922a274204e49fe0c5bbb077cd1d21de3b1e61dc95
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231302|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_152c962a53f5f57b

Sources EV-9c62393f18d4121cd7a89819
Evidence SHA-256 f89c193baf228f2d17ddc1922a274204e49fe0c5bbb077cd1d21de3b1e61dc95
행 SHA-256 4d9d69b6603f1dc0fe47b2cb34fc6cd7f352b5b2be08ce4885341f5cec39e44d
Source snapshots by date · KOR · kepco_planned

154kV 광석(물왕)S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_8b9d96c0e45f45f7
stable_project_keyprjtDef:231302:ESB
project_definition231302
first_region_codeESB
manual_source_formatfalse
project_name154kV 광석(물왕)S/S 건설사업
project_name_list154kV 광석S/S 건설사업
purpose시흥시 장현,목감택지개발지구내 전력공급
project_region_detail경기도 시흥시
project_period_raw2017.01~2027.12
project_scale_raw154KV MTR 60MVA×2BANK, 170KV GIS×10CCT
responsible_office_raw경인건설본부/남서울인천건설지사
equipment_type변전
headquarters경인건설본부
office남서울인천건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_152c962a53f5f57b
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_8b9d96c0e45f45f7

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_8b9d96c0e45f45f7

Sources EV-eab8001f13ba914cbeb0a08d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 2fb4a3eaef3a4c061a023976f378bd5c4865f4d70b167ef628420ab54c3c8419

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel