POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 19items · current page 1–19 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-872f21e40351726fa4df91eb
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_2cada8450c261d97
stable_project_keyprjtDef:232651:ESB
project_definition232651
first_region_codeESB
manual_source_formatfalse
project_name154kV 북남원분기T/L 건설사업
project_name_list154kV 북남원분기 송전선로 건설사업
purpose154KV 북남원분기 송전선로 건설사업
project_region_detail전북특별자치도 남원시
project_period_raw2024.07~2030.12
project_scale_rawPIAC 410 X 4C X 2KM
responsible_office_raw중부건설본부/전북건설지사
equipment_type가공송전
headquarters중부건설본부
office전북건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_c491c16305e538e8
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_2cada8450c261d97

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_2cada8450c261d97

Sources EV-872f21e40351726fa4df91eb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 0626c5d8aa5afbe38b609641fcb30ad36500cf1211fe3f076a415489f5884413
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-11
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-06
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-12
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-07
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-10
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-09
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-11
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeroute_or_site_confirmation
date2024-07
date_precisionmonth
assertionsource_stated_candidate
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2030-12
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-07
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2026-01
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2024-07
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source schedule candidates · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-03
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232651|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source snapshots by date · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_c491c16305e538e8
stable_project_idkproj_2cada8450c261d97
source_key202609|232651|ESB
basic_ym202609
source_stage_raw계획확정-사업승인전
project_name_list154kV 북남원분기 송전선로 건설사업
project_name_detail154kV 북남원분기T/L 건설사업
region_summary_raw전북특별자치도 남원시등 1 지역
equipment_type_raw가공송전
headquarters_raw중부건설본부
office_raw전북건설지사
section_fields
Project purpose
  • 154KV 북남원분기 송전선로 건설사업
Project region
  • 전북특별자치도 남원시
Project period
  • 2024.07~2030.12
사업 규모
  • PIAC 410 X 4C X 2KM
담당 사업소
  • 중부건설본부/전북건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 2024.07 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
[진행경과] □ '23.05 : 제10차 장기 송변전설비계획 신규 반영 □ '24.07 : 전력영향평가 용역 착수 □ '24.11 : 지자체 및 사매면 이장단 대상 사업설명회 시행 완료 □ '24.12 : 입지선정위원회 위원 추천 요청(남원시청) □ '25.03 : 입지선정위원회 구성완료 □ '25.05 : 주민대상 사업설명 시행(6개 마을 및 발전협의회) □ '25.06 : 사매면 이장단 및 발전협의회 대상 사업설명시행 □ '25.07 : 남원시장 대상 사업설명시행 □ '25.08 : 남원시 기원지원과 협의 □ '25.09 : 사매면(지자체,주민) 대상 사업설명 및 사업추진경과 공유 □ '25.10 : 강성민원(양계장 주인) 개별면담시행, 혼불문학제 지원, 남원시청 기업정책과장 대상 변전소 입지 관련 협의 □ '25.11 : 사업 필요성 자료 보충 후 남원시청 부시장 협의 추진 □ '26.01 : 변전소 산단 內 유치 관련 남원시장 보고결과(기업정책과→남원시장) 공유 ○ 산단 內 반영 가능 입장, 정확한 위치는 선거후 구체화 협의예정
future_plan_redacted□ 향후계획 [진행경과] □ '23.05 : 제10차 장기 송변전설비계획 신규 반영 □ '24.07 : 전력영향평가 용역 착수 □ '24.11 : 지자체 및 사매면 이장단 대상 사업설명회 시행 완료 □ '24.12 : 입지선정위원회 위원 추천 요청(남원시청) □ '25.03 : 입지선정위원회 구성완료 □ '25.05 : 주민대상 사업설명 시행(6개 마을 및 발전협의회) □ '25.06 : 사매면 이장단 및 발전협의회 대상 사업설명시행 □ '25.07 : 남원시장 대상 사업설명시행 □ '25.08 : 남원시 기원지원과 협의 □ '25.09 : 사매면(지자체,주민) 대상 사업설명 및 사업추진경과 공유 □ '25.10 : 강성민원(양계장 주인) 개별면담시행, 혼불문학제 지원, 남원시청 기업정책과장 대상 변전소 입지 관련 협의 □ '25.11 : 사업 필요성 자료 보충 후 남원시청 부시장 협의 추진 □ '26.01 : 변전소 산단 內 유치 관련 남원시장 보고결과(기업정책과→남원시장) 공유 ○ 산단 內 반영 가능 입장, 정확한 위치는 선거후 구체화 협의예정
attachment_count0
source_detail_sha256bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|232651|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_c491c16305e538e8

Sources EV-7c73a4996d7f39570eb7e38c
Evidence SHA-256 bf1a777d2f5dcbaf482435c265dfa1bcfa4fcb178154dcf3d7e1f592978d738a
행 SHA-256 94bfedc708d6a6aaed84d996c9b1b14467ec2f828008725b22b1d99846787478
Source snapshots by date · KOR · kepco_planned

154kV 북남원분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_2cada8450c261d97
stable_project_keyprjtDef:232651:ESB
project_definition232651
first_region_codeESB
manual_source_formatfalse
project_name154kV 북남원분기T/L 건설사업
project_name_list154kV 북남원분기 송전선로 건설사업
purpose154KV 북남원분기 송전선로 건설사업
project_region_detail전북특별자치도 남원시
project_period_raw2024.07~2030.12
project_scale_rawPIAC 410 X 4C X 2KM
responsible_office_raw중부건설본부/전북건설지사
equipment_type가공송전
headquarters중부건설본부
office전북건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_c491c16305e538e8
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_2cada8450c261d97

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_2cada8450c261d97

Sources EV-872f21e40351726fa4df91eb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 0626c5d8aa5afbe38b609641fcb30ad36500cf1211fe3f076a415489f5884413

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel