POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 5items · current page 1–5 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 복정S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-06d01d40e896351e9bccd23d
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_8bf105957a2be437
stable_project_keyprjtDef:231185:ESB
project_definition231185
first_region_codeESB
manual_source_formatfalse
project_name154kV 복정S/S 건설사업
project_name_list154kV 복정S/S 건설사업
purpose성남복정 신규부하 공급 및 인근변전소 부?
project_region_detail경기도 성남시 수정구
project_period_raw2008.06~2026.06
project_scale_raw154/23KV 15/20MVA X 3대 2BANK
responsible_office_raw경인건설본부/직할
equipment_type변전
headquarters경인건설본부
office직할
current_stage_raw공사착수-사업완료전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_61c78d14627585fb
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text공사착수-사업완료전
source_record_idstable_project_id:kproj_8bf105957a2be437

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_8bf105957a2be437

Sources EV-06d01d40e896351e9bccd23d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 6f09d42ddcb0841696459c515aa9327d3935a1c8c1e89e545b2f5333fd268777
Source schedule candidates · KOR · kepco_planned

154kV 복정S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2008-06
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231185|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_61c78d14627585fb

Sources EV-03bf73eaf11760762a20cd85
Evidence SHA-256 c26e1b5ccbda0ac8024885531e481bfd4de338ca5dd57477733056cafc994792
행 SHA-256 fb8ed1c31c3c308f9f274ab065ed6c1d2f9a87e8c8884504d5d5b7d85dba7ac6
Source schedule candidates · KOR · kepco_planned

154kV 복정S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2026-06
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231185|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_61c78d14627585fb

Sources EV-03bf73eaf11760762a20cd85
Evidence SHA-256 c26e1b5ccbda0ac8024885531e481bfd4de338ca5dd57477733056cafc994792
행 SHA-256 fb8ed1c31c3c308f9f274ab065ed6c1d2f9a87e8c8884504d5d5b7d85dba7ac6
Source snapshots by date · KOR · kepco_planned

154kV 복정S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_61c78d14627585fb
stable_project_idkproj_8bf105957a2be437
source_key202609|231185|ESB
basic_ym202609
source_stage_raw공사착수-사업완료전
project_name_list154kV 복정S/S 건설사업
project_name_detail154kV 복정S/S 건설사업
region_summary_raw경기도 성남시 수정구등 1 지역
equipment_type_raw변전
headquarters_raw경인건설본부
office_raw직할
section_fields
Project purpose
  • 성남복정 신규부하 공급 및 인근변전소 부?
Project region
  • 경기도 성남시 수정구
Project period
  • 2008.06~2026.06
사업 규모
  • 154/23KV 15/20MVA X 3대 2BANK
담당 사업소
  • 경인건설본부/직할
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정: 2021.11
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
전원개발사업 실시계획 승인
사업설계
  • 설계용역: 기본설계: 2022.06 ~ 2022.08 실시설계: 2024.01 ~ 2024.07 설계담당자: [redacted]
건설공사 개요
  • 공사 착공: 2024.10 공사 기간: 2024.10 ~ 2026.06 감독자: [redacted], 실적): 76, 96
○ 진행경과 - '08.06 : 사업 착수 - '21.11 : 경과지 확정[경기도 성남시 수정구 복정동 7(성남복정1지구 內)] - '22.08 : 기본설계 완료 - '23.11 : 용지매수 완료 - '24.07 : 실시설계 완료 - '24.08 : 토건공사 착공 - '24.11 : 변전공사 착공 ○ 향후계획 - '26.06 : 변전소 가압
future_plan_redacted□ 향후계획 ○ 진행경과 - '08.06 : 사업 착수 - '21.11 : 경과지 확정[경기도 성남시 수정구 복정동 7(성남복정1지구 內)] - '22.08 : 기본설계 완료 - '23.11 : 용지매수 완료 - '24.07 : 실시설계 완료 - '24.08 : 토건공사 착공 - '24.11 : 변전공사 착공 ○ 향후계획 - '26.06 : 변전소 가압
attachment_count0
source_detail_sha256c26e1b5ccbda0ac8024885531e481bfd4de338ca5dd57477733056cafc994792
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231185|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_61c78d14627585fb

Sources EV-03bf73eaf11760762a20cd85
Evidence SHA-256 c26e1b5ccbda0ac8024885531e481bfd4de338ca5dd57477733056cafc994792
행 SHA-256 fb8ed1c31c3c308f9f274ab065ed6c1d2f9a87e8c8884504d5d5b7d85dba7ac6
Source snapshots by date · KOR · kepco_planned

154kV 복정S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_8bf105957a2be437
stable_project_keyprjtDef:231185:ESB
project_definition231185
first_region_codeESB
manual_source_formatfalse
project_name154kV 복정S/S 건설사업
project_name_list154kV 복정S/S 건설사업
purpose성남복정 신규부하 공급 및 인근변전소 부?
project_region_detail경기도 성남시 수정구
project_period_raw2008.06~2026.06
project_scale_raw154/23KV 15/20MVA X 3대 2BANK
responsible_office_raw경인건설본부/직할
equipment_type변전
headquarters경인건설본부
office직할
current_stage_raw공사착수-사업완료전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_61c78d14627585fb
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text공사착수-사업완료전
source_record_idstable_project_id:kproj_8bf105957a2be437

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_8bf105957a2be437

Sources EV-06d01d40e896351e9bccd23d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 6f09d42ddcb0841696459c515aa9327d3935a1c8c1e89e545b2f5333fd268777

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel