Beech Street/City Road
Connection register · built
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 30 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-33189ff1f40548d2235e8d3a |
| MW Increase / Decrease | 0 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-33189ff1f40548d2235e8d3a |
| Cumulative Total Capacity (MW) | 30 MW | Original source column definition · project stage · Built As-of date 2026-10-01 Sources EV-33189ff1f40548d2235e8d3a |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Beech Street/City Road |
| Customer Name | CITIGEN (LONDON) LIMITED |
| Connection Site | Beech Street/City Road Substation |
| Stage | Not obtained |
| MW Connected | 30.00 |
| MW Increase / Decrease | 0.00 |
| Cumulative Total Capacity (MW) | 30.00 |
| MW Effective From | Not obtained |
| Project Status | Built |
| Agreement Type | Embedded |
| HOST TO | NGET |
| Plant Type | CHP (Combined Heat and Power) |
| Project ID | a0l4L0000005iUtQAI |
| Project Number | PRO-000027 |
| Gate | Not obtained |
| Original text | Built |
| source_record_id | csv:row:143 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:143
Sources EV-33189ff1f40548d2235e8d3aEvidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 60530efa0a4c0cd8529d8423c5fc7e6444c7fa0989ee259db11e10dfdad2db40
Usage terms NESO Open Data Licence