Bicker Fen
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-2bc60252501386e2e5f216e6 |
| MW Increase / Decrease | 400 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-2bc60252501386e2e5f216e6 |
| Cumulative Total Capacity (MW) | 400 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-2bc60252501386e2e5f216e6 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Bicker Fen |
| Customer Name | IB VOGT UK LTD |
| Connection Site | Trent Valley South Connection Node C 400kV Substation |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 400.00 |
| Cumulative Total Capacity (MW) | 400.00 |
| MW Effective From | 2034-10-31 |
| Project Status | Scoping |
| Agreement Type | Direct Connection |
| HOST TO | NGET |
| Plant Type | Energy Storage System;PV Array (Photo Voltaic/solar) |
| Project ID | a0l8e000001HxlxAAC |
| Project Number | PRO-004295 |
| Gate | 1 |
| Original text | Scoping |
| source_record_id | csv:row:184 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:184
Sources EV-2bc60252501386e2e5f216e6Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 eab9ffb400530b365ca52fcc778374033a87858f3a56f81e59e9dfcd19eab105
Usage terms NESO Open Data Licence