Dronley Solar
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-9752387e7b2162fba4f162fd |
| MW Increase / Decrease | 50 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-9752387e7b2162fba4f162fd |
| Cumulative Total Capacity (MW) | 50 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-9752387e7b2162fba4f162fd |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Dronley Solar |
| Customer Name | GREENTECH PROJECTS HOLDING UK LIMITED |
| Connection Site | Lyndhurst GSP |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 50.00 |
| Cumulative Total Capacity (MW) | 50.00 |
| MW Effective From | 2031-10-31 |
| Project Status | Scoping |
| HOST TO | SHET |
| Plant Type | PV Array (Photo Voltaic/solar) |
| Project ID | a0l8e000001HoTsAAK |
| Project Number | PRO-004078 |
| Gate | Not obtained |
| Original text | Scoping |
| source_record_id | csv:row:179 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:179
Sources EV-9752387e7b2162fba4f162fdEvidence SHA-256 2feb369e26e2a57bf5656824c32190410d8889b1e9d9a06a1bbb6c2c3e49f21b
행 SHA-256 e5a90e931d01e0ea191c681989c0eabc8ddf9b97415e1452eb62d8bf02c400e6
Usage terms NESO Open Data Licence