Binn Solar Farm
Connection register · scoping
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| MW Connected | 0 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-4f2237bd79f0cd1e9d06286d |
| MW Increase / Decrease | 30 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-4f2237bd79f0cd1e9d06286d |
| Cumulative Total Capacity (MW) | 30 MW | Original source column definition · project stage · Scoping As-of date 2026-10-01 Sources EV-4f2237bd79f0cd1e9d06286d |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Project Name | Binn Solar Farm |
| Customer Name | TRIO POWER LIMITED |
| Connection Site | Abernethy 2 GSP |
| Stage | Not obtained |
| MW Connected | 0.00 |
| MW Increase / Decrease | 30.00 |
| Cumulative Total Capacity (MW) | 30.00 |
| MW Effective From | 2035-10-31 |
| Project Status | Scoping |
| HOST TO | SHET |
| Plant Type | Energy Storage System;PV Array (Photo Voltaic/solar) |
| Project ID | a0lJ9000000POjoIAG |
| Project Number | PRO-006117 |
| Gate | Not obtained |
| Original text | Scoping |
| source_record_id | csv:row:66 |
Location: Coordinates not obtained · no map marker
Sources, reference dates and retrieval dates 1items
Data Source 2026-10-01 · Retrieved 2026-10-05
Supported by National Energy SO Open Data
Source location csv:row:66
Sources EV-4f2237bd79f0cd1e9d06286dEvidence SHA-256 2feb369e26e2a57bf5656824c32190410d8889b1e9d9a06a1bbb6c2c3e49f21b
행 SHA-256 9d91fb10b92f33fcad1f122bd5cf53a0dfea1f1aeff18c6c6f63bd8d81bc4248
Usage terms NESO Open Data Licence