Cooperative Solar Two-Fayette / PV2
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 40 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-a150500c3e5727fc91b7e720 |
| Net Summer Capacity (MW) | 40 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-a150500c3e5727fc91b7e720 |
| Net Winter Capacity (MW) | 40 MW | Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-a150500c3e5727fc91b7e720 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 5580 |
| Entity Name | East Kentucky Power Coop, Inc |
| Plant ID | 69741 |
| Plant Name | Cooperative Solar Two-Fayette |
| Google Map | Map |
| Bing Map | Map |
| Plant State | KY |
| County | Fayette |
| Balancing Authority Code | PJM |
| Sector | Electric Utility |
| Generator ID | PV2 |
| Nameplate Capacity (MW) | 40 |
| Net Summer Capacity (MW) | 40 |
| Net Winter Capacity (MW) | 40 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 11 |
| Planned Operation Year | 2027 |
| Status | (U) Under construction, less than or equal to 50 percent complete |
| Latitude | 38.035403 |
| Longitude | -84.31579 |
| Original text | (U) Under construction, less than or equal to 50 percent complete |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:1147 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:2123
Sources EV-c82886a679e45e9b516b7e81Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 17cd8dc839b9d9ffc1da5c095b81fe5f50c94c9694f3c56562425af96e12116b
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:1147
Sources EV-a150500c3e5727fc91b7e720Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 4f5b9e602a6c4bc4b4a317c14157213a703eee28440b1d2bf15f530aa2f65394
Usage terms US government public domain