Cold Creek Solar Park / CLCSP
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 100 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-e0eddb12108d7b0c264f6a23 |
| Net Summer Capacity (MW) | 100 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-e0eddb12108d7b0c264f6a23 |
| Net Winter Capacity (MW) | 100 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-e0eddb12108d7b0c264f6a23 |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 5109 |
| Entity Name | DTE Electric Company |
| Plant ID | 69471 |
| Plant Name | Cold Creek Solar Park |
| Google Map | Map |
| Bing Map | Map |
| Plant State | MI |
| County | Branch |
| Balancing Authority Code | MISO |
| Sector | Electric Utility |
| Generator ID | CLCSP |
| Nameplate Capacity (MW) | 100 |
| Net Summer Capacity (MW) | 100 |
| Net Winter Capacity (MW) | 100 |
| Technology | Solar Photovoltaic |
| Energy Source Code | SUN |
| Prime Mover Code | PV |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (TS) Construction complete, but not yet in commercial operation |
| Latitude | 41.938 |
| Longitude | -85.003 |
| Original text | (TS) Construction complete, but not yet in commercial operation |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:126 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:1885
Sources EV-2fa640680a5456d0b1d12d03Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 9556d343a297f551078eb7a56c63e78c050b6666e32d7ed7844be36f942aa46e
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:126
Sources EV-e0eddb12108d7b0c264f6a23Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 237e6b6c411326ec76f330c2f292f7c34359618fbf68c3788c026882b479dfb3
Usage terms US government public domain