Desert Bloom / DSBLM
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 150 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-34df58ab26adc458e19e641b |
| Net Summer Capacity (MW) | 150 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-34df58ab26adc458e19e641b |
| Net Winter Capacity (MW) | 150 MW | Original source column definition · Generator · (TS) Construction complete, but not yet in commercial operation As-of date 2026-08 Sources EV-34df58ab26adc458e19e641b |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 67365 |
| Entity Name | RE Desert Bloom LLC |
| Plant ID | 69290 |
| Plant Name | Desert Bloom |
| Google Map | Map |
| Bing Map | Map |
| Plant State | AZ |
| County | Maricopa |
| Balancing Authority Code | DOPD |
| Sector | IPP Non-CHP |
| Generator ID | DSBLM |
| Nameplate Capacity (MW) | 150 |
| Net Summer Capacity (MW) | 150 |
| Net Winter Capacity (MW) | 150 |
| Technology | Batteries |
| Energy Source Code | MWH |
| Prime Mover Code | BA |
| Planned Operation Month | 9 |
| Planned Operation Year | 2026 |
| Status | (TS) Construction complete, but not yet in commercial operation |
| Latitude | 33.70299 |
| Longitude | -112.3219 |
| Original text | (TS) Construction complete, but not yet in commercial operation |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:116 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:1786
Sources EV-63838e3d2dba8184492e68c1Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 cbb63781af0f03df93c4e3da95744161ee46479c9c8b5bc009f2989030008c70
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:116
Sources EV-34df58ab26adc458e19e641bEvidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 9491e18d547b59c28a578f18910669058e7a4aad09ba3017ddfc0d0b76277c71
Usage terms US government public domain