Grenada Lake Hydroelectric Project / NA1
Generator · Plan
| Metric or condition | Source value | Basis, scope and stage |
|---|---|---|
| Nameplate Capacity (MW) | 5 MW | Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-4a32920fcc8f978682b051bf |
| Net Summer Capacity (MW) | 4 MW | Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-4a32920fcc8f978682b051bf |
| Net Winter Capacity (MW) | 3 MW | Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-4a32920fcc8f978682b051bf |
Detailed source fields
| Original source field | Published value or condition |
|---|---|
| Entity ID | 61906 |
| Entity Name | Rye Development |
| Plant ID | 62430 |
| Plant Name | Grenada Lake Hydroelectric Project |
| Google Map | Map |
| Bing Map | Map |
| Plant State | MS |
| County | Grenada |
| Balancing Authority Code | TVA |
| Sector | IPP Non-CHP |
| Generator ID | NA1 |
| Nameplate Capacity (MW) | 5 |
| Net Summer Capacity (MW) | 4 |
| Net Winter Capacity (MW) | 3 |
| Technology | Conventional Hydroelectric |
| Energy Source Code | WAT |
| Prime Mover Code | HY |
| Planned Operation Month | 4 |
| Planned Operation Year | 2028 |
| Status | (P) Planned for installation, but regulatory approvals not initiated |
| Latitude | 33.808842 |
| Longitude | -89.77246 |
| Original text | (P) Planned for installation, but regulatory approvals not initiated |
| Coordinate accuracy | source_precision_not_independently_surveyed |
| source_record_id | Planned:1493 |
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:325
Sources EV-f5f444622fb84656c7f3a67cEvidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 af67a7e1269ac1232be0433813b6263d0ff11e5e854ab9f9a82ccfb728bfd765
Usage terms US government public domain
Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Planned:1493
Sources EV-4a32920fcc8f978682b051bfEvidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 a92da32613075b41da85643fcfa8b71e1943998e782bc16f8bf3fe767beb1686
Usage terms US government public domain