POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 48items · current page 1–48 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-b960aa7c3848503a2d9343bb
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_e784c5caf1404c45
stable_project_keyprjtDef:232572:ESB
project_definition232572
first_region_codeESB
manual_source_formatfalse
project_name154kV 다인분기T/L 건설사업
project_name_list154kV 다인분기T/L 건설사
purpose의성지역 재생E 연계
project_region_detail경상북도 의성군
project_period_raw2021.10~2027.06
project_scale_raw154KV ACSR 410㎟ × S × 4C, 약 25.833KM
responsible_office_raw남부건설본부/대구경북건설지사
equipment_type가공송전
headquarters남부건설본부
office대구경북건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_38c23106f14968cb
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_e784c5caf1404c45

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_e784c5caf1404c45

Sources EV-b960aa7c3848503a2d9343bb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 27fd6995bf2a864943c23246a9001be1444ec61d300673c83943515024d82e8a
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-03
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2021-10
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-09
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeroute_or_site_confirmation
date2024-01
date_precisionmonth
assertionsource_stated_candidate
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-09
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-05
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2026-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2006-01
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeimplementation_plan_approval
date2026-07
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-09
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-03
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeimplementation_plan_approval
date2025-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-05
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-10
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2027-06
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typedesign_completion
date2025-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-08
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-04
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2025-06
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeenergization
date2029-12
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-01
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2026-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-10
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-09
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-12
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-04
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-03
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-09
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeconstruction_start
date2026-10
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-07
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeroute_or_site_confirmation
date2023-12
date_precisionmonth
assertionsource_stated_candidate
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-01
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2021-10
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-11
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-05
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-12
date_precisionmonth
assertionsource_stated_candidate
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-01
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-06
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeroute_or_site_confirmation
date2023-12
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source schedule candidates · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-09
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|232572|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source snapshots by date · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_38c23106f14968cb
stable_project_idkproj_e784c5caf1404c45
source_key202609|232572|ESB
basic_ym202609
source_stage_raw계획확정-사업승인전
project_name_list154kV 다인분기T/L 건설사
project_name_detail154kV 다인분기T/L 건설사업
region_summary_raw경상북도 의성군등 1 지역
equipment_type_raw가공송전
headquarters_raw남부건설본부
office_raw대구경북건설지사
section_fields
Project purpose
  • 의성지역 재생E 연계
Project region
  • 경상북도 의성군
Project period
  • 2021.10~2027.06
사업 규모
  • 154KV ACSR 410㎟ × S × 4C, 약 25.833KM
담당 사업소
  • 남부건설본부/대구경북건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 2022.12 입지선정위원회 구성시기: 2023.05 참여 위원 수 : 20 지장유무 조회: 2023.09~2024.01 경과지(부지) 확정: 2023.12
환경/재해 영향평가
  • 환경영향평가: 2024.05 ~ 재해영향평가: 2024.04 ~
주민의견 수렴
  • 지자체 공고 열람: 2024.09 ~ 2024.10 설명회·공청회: 2024.09 자체설명회: 2023.01 ~ 2024.09
입지선정 및 주민의견 수렴 주요 내용
[진행경과] □ ‘21.10 : 제9차 장기송변전설비계획 반영 □ ‘22.12 : 전력영향평가 및 경과지설계용역 계약 및 착수 □ ‘23.01 : 지자체 사업 설명회(의성군청) □ ‘23.02 : 지자체 사업 설명회(다인면, 단북면, 안계면, 안사면) □ ‘23.03~04 : 주민대표 사업 설명(면 단위 이장단협의회) □ ‘23.03~05 : 입지선정위원회 구성 관련 관계자(군/면) 협의 및 구성 □ ‘23.05 : 입지선정위원회 착수 회의(1차) 시행 □ ‘23.06 : 입지선정위원회 2차 회의 시행(최적 경과대역 확정) □ ‘23.07 : 지자체 사업 설명회(의성군의회) □ ‘23.08 : 입지선정위원회 3차 회의 시행(후보 경과지 선정) □ ‘23.09 : 입지선정위원회 4차 회의 시행(최적 경과지 선정) □ ‘23.10 : 마을별 최적입지에 대한 주민의견 수렴(8/9개리) 및 지장유무 조회 □ ‘23.11~12 : 최적경과지 설계측량 □ ‘23.12 : 입지선정위원회 5차 회의 시행(최적경과지 확정) □ ‘24.01 : 입지확정위원회 시행 □ ‘24.02 : 측량완료 □ ‘24.04 : 자재운반방법 선정용역 착수 □ ‘24.05 : 소규모 환경·재해영향평가 착수 □ ‘24.09 : 사업시행계획서 공고·열람(9/23~10/11) 및 주민설명회 시행(9/25) □ ‘25.03 : 다인면 덕미1리 대상 사업설명회 시행 □ ‘25.06 : 06.16(월) 14:00 공청회 개최 □ ‘25.08 : 실시계획 승인 신청 □ ‘25.08 : 실시설계 완료 □ ‘26.02 : 공사 계약 의뢰(종합심사낙찰제) □ ‘26.05 : 공사 입찰공고(5.4) [향후계획] □ ‘26.07 : 실시계획 승인 □ ‘26.10 : 가공공사 착공 □ ‘29.12 : 가압
future_plan_redacted□ 향후계획 [진행경과] □ ‘21.10 : 제9차 장기송변전설비계획 반영 □ ‘22.12 : 전력영향평가 및 경과지설계용역 계약 및 착수 □ ‘23.01 : 지자체 사업 설명회(의성군청) □ ‘23.02 : 지자체 사업 설명회(다인면, 단북면, 안계면, 안사면) □ ‘23.03~04 : 주민대표 사업 설명(면 단위 이장단협의회) □ ‘23.03~05 : 입지선정위원회 구성 관련 관계자(군/면) 협의 및 구성 □ ‘23.05 : 입지선정위원회 착수 회의(1차) 시행 □ ‘23.06 : 입지선정위원회 2차 회의 시행(최적 경과대역 확정) □ ‘23.07 : 지자체 사업 설명회(의성군의회) □ ‘23.08 : 입지선정위원회 3차 회의 시행(후보 경과지 선정) □ ‘23.09 : 입지선정위원회 4차 회의 시행(최적 경과지 선정) □ ‘23.10 : 마을별 최적입지에 대한 주민의견 수렴(8/9개리) 및 지장유무 조회 □ ‘23.11~12 : 최적경과지 설계측량 □ ‘23.12 : 입지선정위원회 5차 회의 시행(최적경과지 확정) □ ‘24.01 : 입지확정위원회 시행 □ ‘24.02 : 측량완료 □ ‘24.04 : 자재운반방법 선정용역 착수 □ ‘24.05 : 소규모 환경·재해영향평가 착수 □ ‘24.09 : 사업시행계획서 공고·열람(9/23~10/11) 및 주민설명회 시행(9/25) □ ‘25.03 : 다인면 덕미1리 대상 사업설명회 시행 □ ‘25.06 : 06.16(월) 14:00 공청회 개최 □ ‘25.08 : 실시계획 승인 신청 □ ‘25.08 : 실시설계 완료 □ ‘26.02 : 공사 계약 의뢰(종합심사낙찰제) □ ‘26.05 : 공사 입찰공고(5.4) [향후계획] □ ‘26.07 : 실시계획 승인 □ ‘26.10 : 가공공사 착공 □ ‘29.12 : 가압
attachment_count0
source_detail_sha2562a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|232572|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_38c23106f14968cb

Sources EV-398335cb935f7fda5bed349c
Evidence SHA-256 2a1047c8f6bd90d6713579af5f24d1fbb4011c728d53411ede79d6ad8f0b91d2
행 SHA-256 59b4b419794809698c999b7f7c409b10a7c1319ef656c6f33ee9a9b79f8cb948
Source snapshots by date · KOR · kepco_planned

154kV 다인분기T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_e784c5caf1404c45
stable_project_keyprjtDef:232572:ESB
project_definition232572
first_region_codeESB
manual_source_formatfalse
project_name154kV 다인분기T/L 건설사업
project_name_list154kV 다인분기T/L 건설사
purpose의성지역 재생E 연계
project_region_detail경상북도 의성군
project_period_raw2021.10~2027.06
project_scale_raw154KV ACSR 410㎟ × S × 4C, 약 25.833KM
responsible_office_raw남부건설본부/대구경북건설지사
equipment_type가공송전
headquarters남부건설본부
office대구경북건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_38c23106f14968cb
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_e784c5caf1404c45

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_e784c5caf1404c45

Sources EV-b960aa7c3848503a2d9343bb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 27fd6995bf2a864943c23246a9001be1444ec61d300673c83943515024d82e8a

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel