POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 5items · current page 1–5 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 광양-세풍T/L 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-c03698786d2cff5e829797f8
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_e205922a61907d20
stable_project_keyprjtDef:232555:ESB
project_definition232555
first_region_codeESB
manual_source_formatfalse
project_name154kV 광양-세풍T/L 건설사업
project_name_list154kV 광양-세풍T/L 건설사업
purpose광양지역 전력공급
project_region_detail전남광주통합특별시 광양시
project_period_raw2024.07~2033.12
project_scale_rawACSR 410㎟×2B×2C×9.7KM
responsible_office_raw중부건설본부/광주전남건설지사
equipment_type가공송전
headquarters중부건설본부
office광주전남건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_709652461081b4d4
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_e205922a61907d20

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_e205922a61907d20

Sources EV-c03698786d2cff5e829797f8
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 18d92abdba7636350e8fa4d7ff8e881fd6804c9f7569c61ca22bbf3817ed3bf6
Source schedule candidates · KOR · kepco_planned

154kV 광양-세풍T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2033-12
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232555|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_709652461081b4d4

Sources EV-9d073123b5abfe3fd8cd14e1
Evidence SHA-256 d27b3f1094e6823b083612b921e20b486ac83c5ae1a9d4a5d710b39b92a56ee4
행 SHA-256 164338bacb490d764f68abdcc03c44f7e876716f8275a49f1ecc8251371ac050
Source schedule candidates · KOR · kepco_planned

154kV 광양-세풍T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2024-07
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|232555|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_709652461081b4d4

Sources EV-9d073123b5abfe3fd8cd14e1
Evidence SHA-256 d27b3f1094e6823b083612b921e20b486ac83c5ae1a9d4a5d710b39b92a56ee4
행 SHA-256 164338bacb490d764f68abdcc03c44f7e876716f8275a49f1ecc8251371ac050
Source snapshots by date · KOR · kepco_planned

154kV 광양-세풍T/L 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_709652461081b4d4
stable_project_idkproj_e205922a61907d20
source_key202609|232555|ESB
basic_ym202609
source_stage_raw계획확정-사업승인전
project_name_list154kV 광양-세풍T/L 건설사업
project_name_detail154kV 광양-세풍T/L 건설사업
region_summary_raw전남광주통합특별시 광양시등 1 지역
equipment_type_raw가공송전
headquarters_raw중부건설본부
office_raw광주전남건설지사
section_fields
Project purpose
  • 광양지역 전력공급
Project region
  • 전남광주통합특별시 광양시
Project period
  • 2024.07~2033.12
사업 규모
  • ACSR 410㎟×2B×2C×9.7KM
담당 사업소
  • 중부건설본부/광주전남건설지사
계획확정
  • 제10차 장기송변전설비계획 반영()
입지선정
  • 전력입지영향평가 용역 착수: 2024.08 입지선정위원회 구성시기: 2026.04 참여 위원 수 : 13 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
  • line □ ’23.06 : 제10차 장기 송·배전설비계획 신규 반영(송전선로) □ ’24.07 :전력영향평가 및 경과지설계 용역 계약 □ ’24.11 : 지자체(광양시) 대상 사업설명 □ ’25.05~11 : 사업대상지역 내 광양읍 9개리 별 이장 대상 사업설명 □ ’26.03 : 입지선정위 구성 완료 및 착수회의 시행 □ ’26.04~06 : 입지선정위 2~3차회의 시행 □ ’26.07 : 최적경과대역 주민설명회 시행 □ ’26.08 : 입지선정위 4차회의 시행(후보경과지 선정) 및 현장답사 시행 □ ’26.09 : 후보경과지 인근마을 대상 사업설명회 시
line ○ 추진실적 - '23. 4 : 제 10차 장기 송변전설비계획 신규반영 - '24. 11 : 광양시 사업설명 - '25. 2 : 광양읍 사업설명 - '25. 4~ 5 : 사업대상지역 내 리별 이장 대상 사업설명 - '26. 3 : 송전선로 건설사업 입지선정위원회 구성완료 - '26. 4 : 입지선정위 착수회의 시행 - '26. 4 : 입지선정위 2차회의 시행 - '26. 6 : 입지선정위 3차회의 시행 - '26. 7 : 최적경과대역 사업설명회 시행 ○ 향후계획 - '26. 8 : 입지선정위 4차회의 시
future_plan_redactedline □ 향후계획 ○ 추진실적 - '23. 4 : 제 10차 장기 송변전설비계획 신규반영 - '24. 11 : 광양시 사업설명 - '25. 2 : 광양읍 사업설명 - '25. 4~ 5 : 사업대상지역 내 리별 이장 대상 사업설명 - '26. 3 : 송전선로 건설사업 입지선정위원회 구성완료 - '26. 4 : 입지선정위 착수회의 시행 - '26. 4 : 입지선정위 2차회의 시행 - '26. 6 : 입지선정위 3차회의 시행 - '26. 7 : 최적경과대역 사업설명회 시행 ○ 향후계획 - '26. 8 : 입지선정위 4차회의 시
attachment_count0
source_detail_sha256d27b3f1094e6823b083612b921e20b486ac83c5ae1a9d4a5d710b39b92a56ee4
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|232555|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_709652461081b4d4

Sources EV-9d073123b5abfe3fd8cd14e1
Evidence SHA-256 d27b3f1094e6823b083612b921e20b486ac83c5ae1a9d4a5d710b39b92a56ee4
행 SHA-256 164338bacb490d764f68abdcc03c44f7e876716f8275a49f1ecc8251371ac050
Source snapshots by date · KOR · kepco_planned

154kV 광양-세풍T/L 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_e205922a61907d20
stable_project_keyprjtDef:232555:ESB
project_definition232555
first_region_codeESB
manual_source_formatfalse
project_name154kV 광양-세풍T/L 건설사업
project_name_list154kV 광양-세풍T/L 건설사업
purpose광양지역 전력공급
project_region_detail전남광주통합특별시 광양시
project_period_raw2024.07~2033.12
project_scale_rawACSR 410㎟×2B×2C×9.7KM
responsible_office_raw중부건설본부/광주전남건설지사
equipment_type가공송전
headquarters중부건설본부
office광주전남건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_709652461081b4d4
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_e205922a61907d20

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_e205922a61907d20

Sources EV-c03698786d2cff5e829797f8
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 18d92abdba7636350e8fa4d7ff8e881fd6804c9f7569c61ca22bbf3817ed3bf6

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel