Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 5items · current page 1–5 · Source records, not unique facilities.
Power assets and projects · KOR · kepco_planned
154kV 서운남-북항 지중T/L 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-12cc3e264b381e1c5b19e68f
Sources EV-a9f871df8d7aa3bba7d5de6c Evidence SHA-256 26732dc0df639f0e040a2f28d6acfc90896ff73c9062903cf70d8dcaf14fd329 행 SHA-256 280e4b392625ed55882aadd67d9f3a077c9564cfb22f6b8f8e3aef75c0a07cd0Source snapshots by date · KOR · kepco_planned
154kV 서운남-북항 지중T/L 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_23c70ff4eecfb234
stable_project_id
kproj_e0171b4282be5399
source_key
202609|233637|ESB
basic_ym
202609
source_stage_raw
계획확정-사업승인전
project_name_list
154kV 서운남-북항 지중송전선로 건설사업
project_name_detail
154kV 서운남-북항 지중T/L 건설사업
region_summary_raw
전남광주통합특별시 목포시등 2 지역
equipment_type_raw
지중송전
headquarters_raw
중부건설본부
office_raw
광주전남건설지사
section_fields
Project purpose
신안지역 재생E 접속용량 확보를 위한 계통보강
Project region
전남광주통합특별시 목포시,무안군
Project period
2021.09~2026.12
사업 규모
154KV XLPE 2000㎟, 2C(D)-6KM
담당 사업소
중부건설본부/광주전남건설지사
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
Sources EV-a9f871df8d7aa3bba7d5de6c Evidence SHA-256 26732dc0df639f0e040a2f28d6acfc90896ff73c9062903cf70d8dcaf14fd329 행 SHA-256 280e4b392625ed55882aadd67d9f3a077c9564cfb22f6b8f8e3aef75c0a07cd0Source snapshots by date · KOR · kepco_planned