Power assets and projects · KOR · kepco_planned
154kV (남양주-왕숙) 전력구 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-5886498ac5769491354d5e7b
Sources EV-d80799ae32896c8ffc86fc47 Evidence SHA-256 3c337554bc1f42855585d2c226126a34374f722d51a29584d9fccb39a1baf9f1 행 SHA-256 ae21feac192cc5889403f9e9562292663e88a19ca56d97459625c735517c03bbSource snapshots by date · KOR · kepco_planned
154kV (남양주-왕숙) 전력구 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_4d58200ac1de4f07
stable_project_id
kproj_8238322dc43783b4
source_key
202609|234771|ESB
basic_ym
202609
source_stage_raw
사업승인-공사착수전
project_name_list
154kV (남양주-왕숙) 전력구 건설사업
project_name_detail
154kV (남양주-왕숙) 전력구 건설사업
region_summary_raw
경기도 남양주시등 1 지역
equipment_type_raw
전력구
headquarters_raw
경인건설본부
office_raw
직할
section_fields
Project purpose
남양주-왕숙 부하 해소
Project region
Namyangju City, Gyeonggi Province
Project period
2024.02~2028.06
사업 규모
전력구 1,336M
담당 사업소
경인건설본부/직할
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
Sources EV-d80799ae32896c8ffc86fc47 Evidence SHA-256 3c337554bc1f42855585d2c226126a34374f722d51a29584d9fccb39a1baf9f1 행 SHA-256 ae21feac192cc5889403f9e9562292663e88a19ca56d97459625c735517c03bbSource snapshots by date · KOR · kepco_planned