POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 5items · current page 1–5 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 산이S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-7bc8bd21b8811473ce0d7a5f
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_702fd9e2bd5bf998
stable_project_keyprjtDef:231633:ESB
project_definition231633
first_region_codeESB
manual_source_formatfalse
project_name154kV 산이S/S 건설사업
project_name_list154kV 산이S/S 건설사업
purpose전라남도 구성지구 개발을 위한 전력공급
project_region_detail전남광주통합특별시 해남군
project_period_raw2024.03~2030.09
project_scale_raw60MVA X 2BANK[최종 4BANK]
responsible_office_raw중부건설본부/광주전남건설지사
equipment_type변전
headquarters중부건설본부
office광주전남건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_8ad4f01c6c22c125
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_702fd9e2bd5bf998

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_702fd9e2bd5bf998

Sources EV-7bc8bd21b8811473ce0d7a5f
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 d245daea52966d7a9ce0a80d946c3e6a04c2ed4f204840af6db5dba8c404cf3a
Source schedule candidates · KOR · kepco_planned

154kV 산이S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2030-09
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231633|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_8ad4f01c6c22c125

Sources EV-6e69ae76a8cfd16b12278819
Evidence SHA-256 a4006ec534bbb4c332084fa7d1ec13ed1ca8869aba0949fe0b4449bf51fa3bae
행 SHA-256 f9576e25df93486b07bc5ea3af75b60d378b08f716f00bb2906c8ac20ddeb9d6
Source schedule candidates · KOR · kepco_planned

154kV 산이S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2024-03
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231633|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_8ad4f01c6c22c125

Sources EV-6e69ae76a8cfd16b12278819
Evidence SHA-256 a4006ec534bbb4c332084fa7d1ec13ed1ca8869aba0949fe0b4449bf51fa3bae
행 SHA-256 f9576e25df93486b07bc5ea3af75b60d378b08f716f00bb2906c8ac20ddeb9d6
Source snapshots by date · KOR · kepco_planned

154kV 산이S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_8ad4f01c6c22c125
stable_project_idkproj_702fd9e2bd5bf998
source_key202609|231633|ESB
basic_ym202609
source_stage_raw사업승인-공사착수전
project_name_list154kV 산이S/S 건설사업
project_name_detail154kV 산이S/S 건설사업
region_summary_raw전남광주통합특별시 해남군등 1 지역
equipment_type_raw변전
headquarters_raw중부건설본부
office_raw광주전남건설지사
section_fields
Project purpose
  • 전라남도 구성지구 개발을 위한 전력공급
Project region
  • 전남광주통합특별시 해남군
Project period
  • 2024.03~2030.09
사업 규모
  • 60MVA X 2BANK[최종 4BANK]
담당 사업소
  • 중부건설본부/광주전남건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
전원개발사업 실시계획 승인
사업설계
  • 설계용역: 기본설계: 실시설계: 설계담당자: [redacted]
[진행경과] □ '24.07 : 입지선정 실무 위원회 구성 및 시행 □ '24.08 : 입지확정위원회 구성 및 시행 □ ‘24.09 : 부지현황측량 요청(→토건부) □ ‘25.02 : 부지확정보고 및 용지업무 추진요청 □ ‘25.03 : 부지매입 관련 사업시행자(BS산업) 면담 □ ‘25.03 : 기본설계 자료제출(→건축 설계부) □ ‘25.07 : 기본설계 완료 및 실시설계 시행 □ ‘25.07 : 토지사용승낙서 배부(사업시행자→한전) □ ‘25.10 : 변전 주자재 발주 시행(M.Tr 및 GIS) □ ‘25.12 : 실시설계 완료 및 일반공사 발주 □ ‘26.03 : 일반공사 계약 완료 및 책임감리용역 발주 □ ‘26.07 : 책임감리용역 계약완료 □ ‘26.08 : 착공전 안전회의 시행 [계획] □ ‘26.10 : 변전공사 착공 □ ‘28.04 : 준공
future_plan_redacted□ 향후계획 [진행경과] □ '24.07 : 입지선정 실무 위원회 구성 및 시행 □ '24.08 : 입지확정위원회 구성 및 시행 □ ‘24.09 : 부지현황측량 요청(→토건부) □ ‘25.02 : 부지확정보고 및 용지업무 추진요청 □ ‘25.03 : 부지매입 관련 사업시행자(BS산업) 면담 □ ‘25.03 : 기본설계 자료제출(→건축 설계부) □ ‘25.07 : 기본설계 완료 및 실시설계 시행 □ ‘25.07 : 토지사용승낙서 배부(사업시행자→한전) □ ‘25.10 : 변전 주자재 발주 시행(M.Tr 및 GIS) □ ‘25.12 : 실시설계 완료 및 일반공사 발주 □ ‘26.03 : 일반공사 계약 완료 및 책임감리용역 발주 □ ‘26.07 : 책임감리용역 계약완료 □ ‘26.08 : 착공전 안전회의 시행 [계획] □ ‘26.10 : 변전공사 착공 □ ‘28.04 : 준공
attachment_count0
source_detail_sha256a4006ec534bbb4c332084fa7d1ec13ed1ca8869aba0949fe0b4449bf51fa3bae
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231633|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_8ad4f01c6c22c125

Sources EV-6e69ae76a8cfd16b12278819
Evidence SHA-256 a4006ec534bbb4c332084fa7d1ec13ed1ca8869aba0949fe0b4449bf51fa3bae
행 SHA-256 f9576e25df93486b07bc5ea3af75b60d378b08f716f00bb2906c8ac20ddeb9d6
Source snapshots by date · KOR · kepco_planned

154kV 산이S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_702fd9e2bd5bf998
stable_project_keyprjtDef:231633:ESB
project_definition231633
first_region_codeESB
manual_source_formatfalse
project_name154kV 산이S/S 건설사업
project_name_list154kV 산이S/S 건설사업
purpose전라남도 구성지구 개발을 위한 전력공급
project_region_detail전남광주통합특별시 해남군
project_period_raw2024.03~2030.09
project_scale_raw60MVA X 2BANK[최종 4BANK]
responsible_office_raw중부건설본부/광주전남건설지사
equipment_type변전
headquarters중부건설본부
office광주전남건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_8ad4f01c6c22c125
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_702fd9e2bd5bf998

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_702fd9e2bd5bf998

Sources EV-7bc8bd21b8811473ce0d7a5f
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 d245daea52966d7a9ce0a80d946c3e6a04c2ed4f204840af6db5dba8c404cf3a

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel