Power assets and projects · KOR · kepco_planned
154kV 배곧(舊정왕#2)S/S 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-9bc19e26d17989369ed9487e
Sources EV-7798c72c043e8d2755e880bc Evidence SHA-256 12e4496f2a90a93082fc6445e550dc11e0268e8b66fdbf5fd8b05dff5a714996 행 SHA-256 5f3d9e07f06196d26631f5395607e1b9aef30e847267d78f282ec314f4902a7cSource snapshots by date · KOR · kepco_planned
154kV 배곧(舊정왕#2)S/S 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_bc41ec63134d9dbc
stable_project_id
kproj_54dc075686b7f1dc
source_key
202609|231419|ESB
basic_ym
202609
source_stage_raw
사업승인-공사착수전
project_name_list
154,000V 배곧변전소 건설사업
project_name_detail
154kV 배곧(舊정왕#2)S/S 건설사업
region_summary_raw
경기도 시흥시등 1 지역
equipment_type_raw
변전
headquarters_raw
경인건설본부
office_raw
남서울인천건설지사
section_fields
Project purpose
변전설비 적기확충으로 안정적 전력공급
Project region
경기도 시흥시
Project period
2017.07~2028.12
사업 규모
154KV M.TR 60MVA X 2BANK(최종 4BANK)
담당 사업소
경인건설본부/남서울인천건설지사
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 2019.10 참여 위원 수 : 경과지(부지) 확정: 2020.03