Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 5items · current page 1–5 · Source records, not unique facilities.
Power assets and projects · KOR · kepco_planned
154kV 북리S/S 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-b2d3906fc4e72cebd080469d
Sources EV-41a8d5bb1aa2f06cb4cf39eb Evidence SHA-256 679367c49a2f577d594f67f3315a9f19c9c8124664dfe9b4664f8a46cece9616 행 SHA-256 4456a81c534ccea2f418012ce10c6a2a5db8dde430c4863bb4aa64aba2047f5dSource snapshots by date · KOR · kepco_planned
154kV 북리S/S 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_0495734fc7322419
stable_project_id
kproj_03ed95ee224e32de
source_key
202609|231611|ESB
basic_ym
202609
source_stage_raw
계획확정-사업승인전
project_name_list
154kV 북리변전소 건설사업
project_name_detail
154kV 북리S/S 건설사업
region_summary_raw
경기도 용인시 처인구등 1 지역
equipment_type_raw
변전
headquarters_raw
경인건설본부
office_raw
경기건설지사
section_fields
Project purpose
변전설비 적기확충으로 안정적 전력공급
Project region
경기도 용인시 처인구
Project period
2023.04~2029.10
사업 규모
154KV M.TR (45/60MVA) X 2BANK
담당 사업소
경인건설본부/경기건설지사
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
Sources EV-41a8d5bb1aa2f06cb4cf39eb Evidence SHA-256 679367c49a2f577d594f67f3315a9f19c9c8124664dfe9b4664f8a46cece9616 행 SHA-256 4456a81c534ccea2f418012ce10c6a2a5db8dde430c4863bb4aa64aba2047f5dSource snapshots by date · KOR · kepco_planned