Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 4items · current page 1–4 · Source records, not unique facilities.
Relationship status: Identity match confirmed · same inherited record Related record power_source:5eaaad6f96a4:power_asset:f9662d22f231 · Relationship evidence
utility supply maximum demand · Campus · as published As-of date 2023-03-26 Sources EV-b4cdc84b8193c832826c2a0f
Detailed source fields
Original source field
Published value or condition
interim_supply_planned
2023-07
full_maximum_demand_planned
2023
Actual energization date
Not obtained
inherited_batch
AIDC-GLOBAL-20261005-DATA-R1-FIX1
eligible_for_exact_contract_mw
false
Verification status
primary_statement
Change type
enriched
Contracting parties
Name
Tenaga Nasional Berhad
Role
electricity_supplier
Organization ID
Not obtained
Verification status
name_in_primary_source_not_registry_verified
Name
GDS IDC Services (Malaysia)
Role
customer
Organization ID
Not obtained
Verification status
name_in_primary_source_not_registry_verified
Primary utility announcement explicitly ties supply to October 2022 ESA, with 16MW interim supply. 85.5MW is described as maximum demand, not quoted as a contract ceiling. Preserve this distinction and historic as-of date.
Sources, reference dates and retrieval dates 2itemswww.tnb.com.my ↗