Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Evidence relationships · USA · primary:a4f79053dc0acceaa499e9f0
River Bend AI data center campus, Louisiana / leased_customer_it_capacity
Not obtained · Source-stated
Relationship status: Source-stated · contract applies to inherited subject Related record r1:power_source:a4f79053dc0a:power_asset:09ebf4d2d031 · Relationship evidence
River Bend AI data center campus, Louisiana / leased_customer_it_capacity
Campus · Official statement
Metric or condition
Source value
Basis, scope and stage
leased_customer_it_capacity
245 MW
leased customer it capacity · Campus · as published As-of date 2025-12-17 Sources EV-978f8daa1ed42f8e2188ea70
Detailed source fields
Original source field
Published value or condition
term_years
15
basis
customer IT lease
utility_capacity_is_separate_MW
330
Supply start date
Not obtained
inherited_batch
AIDC-GLOBAL-20261005-DATA-R1-FIX1
eligible_for_exact_contract_mw
false
Verification status
primary_statement
Change type
enriched
Contracting parties
Name
Hut 8
Role
lessor
Organization ID
Not obtained
Verification status
name_in_primary_source_not_registry_verified
Explicitly IT lease capacity, not utility supply contracted MW. Source identifies Google financial backstop; tenant relationship does not make Google facility operator.
Sources, reference dates and retrieval dates 2itemswww.hut8.com ↗