Evidence relationships · GBR · neso_tec

Corshellach Battery Energy Storage System

Not obtained · Source-stated

Relationship status: Source-stated · Registered connection site
Related record neso:connection_site:c35f82c4377b525a1407753c · Relationship evidence

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
from_kindpower_object
from_idneso_tec:9e439704d40327896e33a53b
to_kindpower_object
to_idneso:connection_site:c35f82c4377b525a1407753c
geometry_relationfalse

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
neso_tec ↗

Data Source 2026-10-01 · Retrieved 2026-10-05

Supported by National Energy SO Open Data

Source location csv:row:467

Sources EV-409d2c48d4dc845e8b1e6229
Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 adce97cf06dd117a13b008bd5ea908ac01cd1e52eb05259780028e5c36a0acfe

Usage terms NESO Open Data Licence

Power assets and projects · GBR · neso_tec

Corshellach Battery Energy Storage System

Connection register · consented

Metric or conditionSource valueBasis, scope and stage
MW Connected0 MWOriginal source column definition · project stage · Consents Approved
As-of date 2026-10-01
Sources EV-409d2c48d4dc845e8b1e6229
MW Increase / Decrease49.9 MWOriginal source column definition · project stage · Consents Approved
As-of date 2026-10-01
Sources EV-409d2c48d4dc845e8b1e6229
Cumulative Total Capacity (MW)49.9 MWOriginal source column definition · project stage · Consents Approved
As-of date 2026-10-01
Sources EV-409d2c48d4dc845e8b1e6229
Detailed source fields
Original source fieldPublished value or condition
Project NameCorshellach Battery Energy Storage System
Customer NameCorshellach Energy Storage Limited
Connection SiteBerryburn 275/33kV GSP Substation
StageNot obtained
MW Connected0.00
MW Increase / Decrease49.90
Cumulative Total Capacity (MW)49.90
MW Effective From2028-10-31
Project StatusConsents Approved
Agreement TypeEmbedded
HOST TOSHET
Plant TypeEnergy Storage System
Project IDa0l4L0000005iXzQAI
Project NumberPRO-002328
Gate2
Original textConsents Approved
source_record_idcsv:row:467

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
neso_tec ↗

Data Source 2026-10-01 · Retrieved 2026-10-05

Supported by National Energy SO Open Data

Source location csv:row:467

Sources EV-409d2c48d4dc845e8b1e6229
Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 adce97cf06dd117a13b008bd5ea908ac01cd1e52eb05259780028e5c36a0acfe

Usage terms NESO Open Data Licence

Source snapshots by date · GBR · neso_tec

Corshellach Battery Energy Storage System

project stage · consented

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Project NameCorshellach Battery Energy Storage System
Customer NameCorshellach Energy Storage Limited
Connection SiteBerryburn 275/33kV GSP Substation
StageNot obtained
MW Connected0.00
MW Increase / Decrease49.90
Cumulative Total Capacity (MW)49.90
MW Effective From2028-10-31
Project StatusConsents Approved
Agreement TypeEmbedded
HOST TOSHET
Plant TypeEnergy Storage System
Project IDa0l4L0000005iXzQAI
Project NumberPRO-002328
Gate2
Original textConsents Approved
source_record_idcsv:row:467

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
neso_tec ↗

Data Source 2026-10-01 · Retrieved 2026-10-05

Supported by National Energy SO Open Data

Source location csv:row:467

Sources EV-409d2c48d4dc845e8b1e6229
Evidence SHA-256 608bac089ceb3fb74f111ee68b68a6f6e44189007e48e8d6ab5410cc48b12480
행 SHA-256 adce97cf06dd117a13b008bd5ea908ac01cd1e52eb05259780028e5c36a0acfe

Usage terms NESO Open Data Licence

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel