Power assets and projects · KOR · kepco_planned
154kV 걸포분기 지중T/L 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-dd4980c18ea491825887a052
Sources EV-3dd9ab42b96dc810fb5b3536 Evidence SHA-256 702e663f2b0e3694958c0a405b1cbfd9dbc5866d24f66dcf2a9087ae4be3d2ea 행 SHA-256 4675c7b328983902efcb0fc7e646ce3a9816549cfa06892fffa9e01b5511cb7dSource snapshots by date · KOR · kepco_planned
154kV 걸포분기 지중T/L 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_9792c9309ffcbd67
stable_project_id
kproj_fd287a7da6e8212c
source_key
202609|233622|ESB
basic_ym
202609
source_stage_raw
계획확정-사업승인전
project_name_list
154kV 걸포분기 지중T/L 건설사업
project_name_detail
154kV 걸포분기 지중T/L 건설사업
region_summary_raw
경기도 김포시등 1 지역
equipment_type_raw
지중송전
headquarters_raw
경인건설본부
office_raw
남서울인천건설지사
section_fields
Project purpose
김포 인근지역 전력계통 보강
Project region
경기도 김포시
Project period
2028.10~2030.06
사업 규모
154KV XLPE 2,000,2C - 3.7KM
담당 사업소
경인건설본부/남서울인천건설지사
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정: