Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 5items · current page 1–5 · Source records, not unique facilities.
Power assets and projects · KOR · kepco_planned
154kV 북김제분기T/L 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-443f1a704ef7e7ab5d23a4e6
Sources EV-33c18dd65b062d649bbecf22 Evidence SHA-256 007036e96a345e701e7b57da9326ffd5813063b486a34ff3bfd0d98e61de1ae4 행 SHA-256 ce60a4b09dfd08492c9bd2b1736ea06e449ff86ba5a4e598ef02e4b74e9c2977Source snapshots by date · KOR · kepco_planned
154kV 북김제분기T/L 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_56cea1f9b57170d2
stable_project_id
kproj_df2b7d12e53e8a8e
source_key
202609|232547|ESB
basic_ym
202609
source_stage_raw
계획확정-사업승인전
project_name_list
154kV 북김제분기 송전선로 건설사업
project_name_detail
154kV 북김제분기T/L 건설사업
region_summary_raw
전북특별자치도 김제시등 1 지역
equipment_type_raw
가공송전
headquarters_raw
중부건설본부
office_raw
전북건설지사
section_fields
Project purpose
신재생E 연계력 확충
Project region
전북특별자치도 김제시
Project period
2018.07~2026.10
사업 규모
PIAC 240㎟XSX4C,0.5KM
담당 사업소
중부건설본부/전북건설지사
계획확정
입지선정
전력입지영향평가 용역 착수: 2024.01 입지선정위원회 구성시기: 참여 위원 수 : 지장유무 조회: 2024.03~2024.04 경과지(부지) 확정: 2024.04
Sources EV-33c18dd65b062d649bbecf22 Evidence SHA-256 007036e96a345e701e7b57da9326ffd5813063b486a34ff3bfd0d98e61de1ae4 행 SHA-256 ce60a4b09dfd08492c9bd2b1736ea06e449ff86ba5a4e598ef02e4b74e9c2977Source snapshots by date · KOR · kepco_planned