POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 19items · current page 1–19 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 남고창S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-4e3b6744b5984b47988f754d
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_d386b04932a3b78f
stable_project_keyprjtDef:231471:ESB
project_definition231471
first_region_codeESB
manual_source_formatfalse
project_name154kV 남고창S/S 건설사업
project_name_list154kV 남고창변전소 건설사업
purpose고창지역 내 분산형전원 연계용량 확보
project_region_detail전북특별자치도 고창군
project_period_raw2018.08~2028.12
project_scale_raw154KV M.TR(80MVA) X 2BANK, 170KV GIS X 10CCT
responsible_office_raw중부건설본부/전북건설지사
equipment_type변전
headquarters중부건설본부
office전북건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_24e8b04b41de8031
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_d386b04932a3b78f

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_d386b04932a3b78f

Sources EV-4e3b6744b5984b47988f754d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 36b73ce7e13807772c60ad458c04ca73ada517299398b122827da1b387029ce2
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-12
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2018-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2020-03
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2018-08
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-08
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2028-12
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2018-07
date_precisionmonth
assertionsource_stated_candidate
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2021-11
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-02
date_precisionmonth
assertionsource_mentioned_unverified
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-05
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeenergization
date2028-12
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2022-07
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeconstruction_start
date2027-01
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2023-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source schedule candidates · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typesource_mentioned_date
date2024-02
date_precisionmonth
assertionplanned
verification_statussource_text_candidate
operational_prooffalse
source_key202609|231471|ESB
migration_statusreused_from_validated_revision1_schedule

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source snapshots by date · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_24e8b04b41de8031
stable_project_idkproj_d386b04932a3b78f
source_key202609|231471|ESB
basic_ym202609
source_stage_raw사업승인-공사착수전
project_name_list154kV 남고창변전소 건설사업
project_name_detail154kV 남고창S/S 건설사업
region_summary_raw전북특별자치도 고창군등 1 지역
equipment_type_raw변전
headquarters_raw중부건설본부
office_raw전북건설지사
section_fields
Project purpose
  • 고창지역 내 분산형전원 연계용량 확보
Project region
  • 전북특별자치도 고창군
Project period
  • 2018.08~2028.12
사업 규모
  • 154KV M.TR(80MVA) X 2BANK, 170KV GIS X 10CCT
담당 사업소
  • 중부건설본부/전북건설지사
계획확정
  • 제08차 장기송변전설비계획 반영(2018.07)
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
전원개발사업 실시계획 승인
사업설계
  • 설계용역: 기본설계: 2022.12 ~ 2023.02 실시설계: 설계담당자: [redacted]
[추진실적] □‘18.08 : 제8차 장기 송변전설비계획 사업반영 □‘20.03 ~‘21.11 : 입지선정위원회 운영 및 부지확정 □‘22.05 : 재생E 연계 대용량변전소 적용 □‘22.07 : 편입부지 소유권 이전 완료 □‘23.02 : 기본설계 심의 완료 □‘22.08 ~‘24.02 : 대용량 표준변전소 모델개발 및 경관심의 완료 □‘24.02 : 변전 주자재 계약 완료 [향후계획] □‘27.01 : 공사 착공 □‘28.12 : 변전소 가압
future_plan_redacted□ 향후계획 [추진실적] □‘18.08 : 제8차 장기 송변전설비계획 사업반영 □‘20.03 ~‘21.11 : 입지선정위원회 운영 및 부지확정 □‘22.05 : 재생E 연계 대용량변전소 적용 □‘22.07 : 편입부지 소유권 이전 완료 □‘23.02 : 기본설계 심의 완료 □‘22.08 ~‘24.02 : 대용량 표준변전소 모델개발 및 경관심의 완료 □‘24.02 : 변전 주자재 계약 완료 [향후계획] □‘27.01 : 공사 착공 □‘28.12 : 변전소 가압
attachment_count0
source_detail_sha2564a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231471|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_24e8b04b41de8031

Sources EV-675b08da70c73af171bb4ee6
Evidence SHA-256 4a51416375c119780c5497822234b7bcd3d9416ac21181797a2e511a3ed01f5a
행 SHA-256 75f1b78c1815bb335e5be9e44bf769d73ea05c740e38e8485d276db5b80e67f8
Source snapshots by date · KOR · kepco_planned

154kV 남고창S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_d386b04932a3b78f
stable_project_keyprjtDef:231471:ESB
project_definition231471
first_region_codeESB
manual_source_formatfalse
project_name154kV 남고창S/S 건설사업
project_name_list154kV 남고창변전소 건설사업
purpose고창지역 내 분산형전원 연계용량 확보
project_region_detail전북특별자치도 고창군
project_period_raw2018.08~2028.12
project_scale_raw154KV M.TR(80MVA) X 2BANK, 170KV GIS X 10CCT
responsible_office_raw중부건설본부/전북건설지사
equipment_type변전
headquarters중부건설본부
office전북건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_24e8b04b41de8031
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_d386b04932a3b78f

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_d386b04932a3b78f

Sources EV-4e3b6744b5984b47988f754d
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 36b73ce7e13807772c60ad458c04ca73ada517299398b122827da1b387029ce2

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel