Power assets and projects · KOR · kepco_planned

154kV 구로#2S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-f7bac3d01ce3232914ae83fb
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_79331d7846b77787
stable_project_keyprjtDef:231569:ESB
project_definition231569
first_region_codeESB
manual_source_formatfalse
project_name154kV 구로#2S/S 건설사업
project_name_list154kV 구로#2S/S 건설사업
purpose변전설비 적기확충으로 안정적 전력공급
project_region_detail서울특별시 구로구
project_period_raw2021.08~2032.12
project_scale_raw154KV M.TR 2BANK(최종 4BANK), 170KV GIS 10CCT
responsible_office_raw경인건설본부/남서울인천건설지사
equipment_type변전
headquarters경인건설본부
office남서울인천건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_caa890013f8522f2
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_79331d7846b77787

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_79331d7846b77787

Sources EV-f7bac3d01ce3232914ae83fb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 73510279269057e4f6c7fed0ac30c94ad61b3fdbf4daa6f8a12608bec8cff768
Source schedule candidates · KOR · kepco_planned

154kV 구로#2S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_end
date2032-12
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231569|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_caa890013f8522f2

Sources EV-88a789e8d4431110f26cfb5f
Evidence SHA-256 325a1992573a48f7261e58e2482fc69d57c9acb812b0531d2010f4f920ca1b75
행 SHA-256 5cf7bedb7426fe514ef763b8081a8ab95098f9c83b6fdf96fe56e71f4e7eddb7
Source schedule candidates · KOR · kepco_planned

154kV 구로#2S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
event_typeproject_period_start
date2021-08
date_precisionmonth
assertionsource_project_period
verification_statussource_field
operational_prooffalse
source_key202609|231569|ESB
migration_statusrevision2_new_snapshot_period_only

No separate metric summary is available. Consult the detailed source fields.

Source-text schedule candidate. Automatic date/event associations remain unverified and do not establish completion or energization.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_caa890013f8522f2

Sources EV-88a789e8d4431110f26cfb5f
Evidence SHA-256 325a1992573a48f7261e58e2482fc69d57c9acb812b0531d2010f4f920ca1b75
행 SHA-256 5cf7bedb7426fe514ef763b8081a8ab95098f9c83b6fdf96fe56e71f4e7eddb7
Source snapshots by date · KOR · kepco_planned

154kV 구로#2S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_caa890013f8522f2
stable_project_idkproj_79331d7846b77787
source_key202609|231569|ESB
basic_ym202609
source_stage_raw계획확정-사업승인전
project_name_list154kV 구로#2S/S 건설사업
project_name_detail154kV 구로#2S/S 건설사업
region_summary_raw서울특별시 구로구등 1 지역
equipment_type_raw변전
headquarters_raw경인건설본부
office_raw남서울인천건설지사
section_fields
Project purpose
  • 변전설비 적기확충으로 안정적 전력공급
Project region
  • 서울특별시 구로구
Project period
  • 2021.08~2032.12
사업 규모
  • 154KV M.TR 2BANK(최종 4BANK), 170KV GIS 10CCT
담당 사업소
  • 경인건설본부/남서울인천건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
1. 진행경과 : 변전소 입지선정 부지협의중 2. 향후계획 - '27.06 : 부지확정완료 - '28.03 : 용지매수완료 - '28.11 : 토건 착공 - '30.10 : 변전소 가압
future_plan_redacted□ 향후계획 1. 진행경과 : 변전소 입지선정 부지협의중 2. 향후계획 - '27.06 : 부지확정완료 - '28.03 : 용지매수완료 - '28.11 : 토건 착공 - '30.10 : 변전소 가압
attachment_count0
source_detail_sha256325a1992573a48f7261e58e2482fc69d57c9acb812b0531d2010f4f920ca1b75
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231569|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_caa890013f8522f2

Sources EV-88a789e8d4431110f26cfb5f
Evidence SHA-256 325a1992573a48f7261e58e2482fc69d57c9acb812b0531d2010f4f920ca1b75
행 SHA-256 5cf7bedb7426fe514ef763b8081a8ab95098f9c83b6fdf96fe56e71f4e7eddb7
Source snapshots by date · KOR · kepco_planned

154kV 구로#2S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_79331d7846b77787
stable_project_keyprjtDef:231569:ESB
project_definition231569
first_region_codeESB
manual_source_formatfalse
project_name154kV 구로#2S/S 건설사업
project_name_list154kV 구로#2S/S 건설사업
purpose변전설비 적기확충으로 안정적 전력공급
project_region_detail서울특별시 구로구
project_period_raw2021.08~2032.12
project_scale_raw154KV M.TR 2BANK(최종 4BANK), 170KV GIS 10CCT
responsible_office_raw경인건설본부/남서울인천건설지사
equipment_type변전
headquarters경인건설본부
office남서울인천건설지사
current_stage_raw계획확정-사업승인전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_caa890013f8522f2
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text계획확정-사업승인전
source_record_idstable_project_id:kproj_79331d7846b77787

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_79331d7846b77787

Sources EV-f7bac3d01ce3232914ae83fb
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 73510279269057e4f6c7fed0ac30c94ad61b3fdbf4daa6f8a12608bec8cff768

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel