POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · KOR · kepco_planned

154kV 남서운S/S 건설사업

Power project · Construction project

Metric or conditionSource valueBasis, scope and stage
project_name_voltage_label154 kVliteral project name label not service voltage · project name · Construction project
As-of date 2026-09
Sources EV-89a2051f328feb7747bd6b83
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_71de2d0fe5653e27
stable_project_keyprjtDef:231722:ESB
project_definition231722
first_region_codeESB
manual_source_formatfalse
project_name154kV 남서운S/S 건설사업
project_name_list154kV 남서운변전소 건설사업
purpose변전설비 적기확충으로 안정적 전력공급
project_region_detailAnseong, Gyeonggi Province
project_period_raw
project_scale_raw154/23KV 15/20MVA X 3대 2BANK
responsible_office_raw경인건설본부/경기건설지사
equipment_type변전
headquarters경인건설본부
office경기건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_bea755c57c4f70dd
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_71de2d0fe5653e27

Location: Coordinates not obtained · no map marker

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_71de2d0fe5653e27

Sources EV-89a2051f328feb7747bd6b83
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 6d62931745e13a36ad868ad48c75b29e12ee0c0d9a03e3d507204bce65feeec7
Source snapshots by date · KOR · kepco_planned

154kV 남서운S/S 건설사업

Project · historical source snapshot

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
snapshot_idksnap_bea755c57c4f70dd
stable_project_idkproj_71de2d0fe5653e27
source_key202609|231722|ESB
basic_ym202609
source_stage_raw사업승인-공사착수전
project_name_list154kV 남서운변전소 건설사업
project_name_detail154kV 남서운S/S 건설사업
region_summary_raw경기도 안성시등 1 지역
equipment_type_raw변전
headquarters_raw경인건설본부
office_raw경기건설지사
section_fields
Project purpose
  • 변전설비 적기확충으로 안정적 전력공급
Project region
  • Anseong, Gyeonggi Province
Project period
사업 규모
  • 154/23KV 15/20MVA X 3대 2BANK
담당 사업소
  • 경인건설본부/경기건설지사
계획확정
입지선정
  • 전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정:
환경/재해 영향평가
  • 환경영향평가: 재해영향평가:
주민의견 수렴
  • 지자체 공고 열람: 설명회·공청회: 자체설명회:
입지선정 및 주민의견 수렴 주요 내용
  • □ '26. 5 : 입지확정위원회 개최
전원개발사업 실시계획 승인
사업설계
  • 설계용역: 기본설계: 실시설계: 설계담당자: [redacted]
□ '31.10 : 변전소 토건공사 착공 □ '32. 2 : 변전소 건설공사 착공
future_plan_redacted□ 향후계획 □ '31.10 : 변전소 토건공사 착공 □ '32. 2 : 변전소 건설공사 착공
attachment_count0
source_detail_sha2563d6a28c5953337ab56648fe37adad78d2f46dd826d96e4247fd58c5e5bbecf09
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
Original reference period202609
source_record_id202609|231722|ESB

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location snapshot_id:ksnap_bea755c57c4f70dd

Sources EV-85014429e4ede1ad66553297
Evidence SHA-256 3d6a28c5953337ab56648fe37adad78d2f46dd826d96e4247fd58c5e5bbecf09
행 SHA-256 a52a802390cac15759a7d301641bd37f3115fae7e2a7e95a37cc180e618dac99
Source snapshots by date · KOR · kepco_planned

154kV 남서운S/S 건설사업

Project · Construction project

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
stable_project_idkproj_71de2d0fe5653e27
stable_project_keyprjtDef:231722:ESB
project_definition231722
first_region_codeESB
manual_source_formatfalse
project_name154kV 남서운S/S 건설사업
project_name_list154kV 남서운변전소 건설사업
purpose변전설비 적기확충으로 안정적 전력공급
project_region_detailAnseong, Gyeonggi Province
project_period_raw
project_scale_raw154/23KV 15/20MVA X 3대 2BANK
responsible_office_raw경인건설본부/경기건설지사
equipment_type변전
headquarters경인건설본부
office경기건설지사
current_stage_raw사업승인-공사착수전
snapshot_count1
active_snapshot_count1
snapshot_ids
  • ksnap_bea755c57c4f70dd
first_seen_at2026-10-02
last_confirmed_at2026-10-02T01:55:13Z
location_precisionregion_only
geometry_semanticsno_verified_geometry
geometryNot obtained
source_list_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusList.do
source_detail_urlhttps://www.kepco.co.kr/home/disclosure/transdisclosure/transstatus/transStatusView.do
Original text사업승인-공사착수전
source_record_idstable_project_id:kproj_71de2d0fe5653e27

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
kepco_planned ↗

Data Source 2026-09 · Retrieved 2026-10-02

한국전력공사 송변전 건설사업 공개자료, 기존 2026-10-02 수집분

Source location stable_project_id:kproj_71de2d0fe5653e27

Sources EV-89a2051f328feb7747bd6b83
Evidence SHA-256 3167e203aa54695eefd19a20bffa2a409c9daab229d61c7a194161481ab40dba
행 SHA-256 6d62931745e13a36ad868ad48c75b29e12ee0c0d9a03e3d507204bce65feeec7

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel