Power assets and projects · KOR · kepco_planned
154kV 산성-복정 전력구 건설사업
Power project · Construction project
Metric or condition
Source value
Basis, scope and stage
project_name_voltage_label
154 kV
literal project name label not service voltage · project name · Construction project As-of date 2026-09 Sources EV-b775ae5376d05e128f7ee67b
Sources EV-a90bacdb5229db0710318484 Evidence SHA-256 d060e6b478626d576860665ec5b6969947c74f4963600e1581fbac051c18d9e3 행 SHA-256 bf02ed28e6d2ba8b8107f73ad34e9f8f614828c3aeb3eb2b2187170ad30351c4Source snapshots by date · KOR · kepco_planned
154kV 산성-복정 전력구 건설사업
Project · historical source snapshot
Metric or condition
Source value
Basis, scope and stage
Detailed source fields
Original source field
Published value or condition
snapshot_id
ksnap_2370fa44cff0a88f
stable_project_id
kproj_08d21691bb38f865
source_key
202609|234646|ESB
basic_ym
202609
source_stage_raw
공사착수-사업완료전
project_name_list
154kV 산성-복정 전력구 건설사업
project_name_detail
154kV 산성-복정 전력구 건설사업
region_summary_raw
경기도 성남시 수정구등 1 지역
equipment_type_raw
전력구
headquarters_raw
경인건설본부
office_raw
직할
section_fields
Project purpose
산성-복정-수서 계통보강
Project region
경기도 성남시 수정구
Project period
2022.03~2028.02
사업 규모
총연장 1,251M
담당 사업소
경인건설본부/직할
계획확정
입지선정
전력입지영향평가 용역 착수: 입지선정위원회 구성시기: 참여 위원 수 : 경과지(부지) 확정: