Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
O'Shaughnessy Hydro
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
35 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-6fdb83cca23ab10ffa026c0a
Detailed source fields
Original source field
Published value or condition
Utility ID
4065
Utility Name
City of Columbus - (OH)
Plant Code
7279
Plant Name
O'Shaughnessy Hydro
Street Address
5959 Glick Rd
City
Dublin
State
OH
Zip
43017
County
Delaware
Latitude
40.153328
Longitude
-83.126719
NERC Region
RFC
Balancing Authority Code
PJM
Balancing Authority Name
PJM Interconnection, LLC
Name of Water Source
O'Shaughnessy Reservoir
Primary Purpose (NAICS Code)
22
Regulatory Status
RE
Sector
1
Sector Name
Electric Utility
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
City of Columbus - (OH)
Transmission or Distribution System Owner ID
4065
Transmission or Distribution System Owner State
OH
Grid Voltage (kV)
35
Energy Storage
N
Natural Gas Storage
X
Liquefied Natural Gas Storage
X
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:2366
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.