Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Amazon Visalia (FAT2)
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
100 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-9d7b00082561bf673d367ac1
Detailed source fields
Original source field
Published value or condition
Utility ID
65043
Utility Name
Madison Energy Investments LLC
Plant Code
69114
Plant Name
Amazon Visalia (FAT2)
Street Address
3315 North Kelsey Street
City
Visalia
State
CA
Zip
93291
County
Tulare
Latitude
36.35914
Longitude
-119.3869
NERC Region
WECC
Balancing Authority Code
CISO
Balancing Authority Name
California Independent System Operator
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
Y
FERC Small Power Producer Docket Number
QF25-965-000
FERC Exempt Wholesale Generator Status
N
Transmission or Distribution System Owner
Southern California Edison Co
Transmission or Distribution System Owner ID
17609
Transmission or Distribution System Owner State
CA
Grid Voltage (kV)
100
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:16033
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.