Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Champaign BESS, LLC
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
138 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-0806700dd0052b0e329ffe66
Detailed source fields
Original source field
Published value or condition
Utility ID
65144
Utility Name
Samsung C&T Renewables, LLC
Plant Code
67917
Plant Name
Champaign BESS, LLC
Street Address
TBD
City
Garden city
State
TX
Zip
79739
County
Glasscock
Latitude
31.871567
Longitude
-101.738384
NERC Region
TRE
Balancing Authority Code
ERCO
Balancing Authority Name
Electric Reliability Council of Texas, Inc.
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Transmission or Distribution System Owner
Oncor Electric Delivery Company LLC
Transmission or Distribution System Owner ID
44372
Transmission or Distribution System Owner State
TX
Grid Voltage (kV)
138
Energy Storage
Y
Natural Gas Storage
N
Liquefied Natural Gas Storage
X
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:14872
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.