Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Walkers Crossroads BESS
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
13.2 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-4b306d19d5315b5fd5051015
Detailed source fields
Original source field
Published value or condition
Utility ID
13683
Utility Name
North Carolina El Member Corp
Plant Code
65246
Plant Name
Walkers Crossroads BESS
Street Address
3816 Burlington Mills Road
City
Wake Forest
State
NC
Zip
27587
County
Wake
Latitude
35.925227
Longitude
-78.50515
NERC Region
SERC
Balancing Authority Code
CPLE
Balancing Authority Name
Duke Energy Progress East
Primary Purpose (NAICS Code)
22
Regulatory Status
RE
Sector
1
Sector Name
Electric Utility
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Transmission or Distribution System Owner
Wake Electric Membership Corp
Transmission or Distribution System Owner ID
19981
Transmission or Distribution System Owner State
NC
Grid Voltage (kV)
13.2
Energy Storage
Y
Natural Gas Storage
N
Liquefied Natural Gas Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:12400
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.