Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Proctor
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
46 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-4c346e3910ed0e0a4da201d6
Detailed source fields
Original source field
Published value or condition
Utility ID
7601
Utility Name
Green Mountain Power Corp
Plant Code
6450
Plant Name
Proctor
Street Address
61 Main Street
City
Proctor
State
VT
Zip
5765
County
Rutland
Latitude
43.662775
Longitude
-73.034023
NERC Region
NPCC
Balancing Authority Code
ISNE
Balancing Authority Name
ISO New England Inc.
Name of Water Source
Otter Creek
Primary Purpose (NAICS Code)
22
Regulatory Status
RE
Sector
1
Sector Name
Electric Utility
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
Green Mountain Power Corp
Transmission or Distribution System Owner ID
7601
Transmission or Distribution System Owner State
VT
Grid Voltage (kV)
46
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:2176
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.