Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Blair Solar
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
23 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-98c675377b644f65c1d01f9b
Detailed source fields
Original source field
Published value or condition
Utility ID
58135
Utility Name
Ecos Energy LLC
Plant Code
64217
Plant Name
Blair Solar
Street Address
150 Bilton Road
City
Somers
State
CT
Zip
6071
County
Tolland
Latitude
42.02956
Longitude
-72.50324
NERC Region
NPCC
Balancing Authority Code
ISNE
Balancing Authority Name
ISO New England Inc.
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
Y
FERC Small Power Producer Docket Number
QF19-1421-000
FERC Exempt Wholesale Generator Status
N
Transmission or Distribution System Owner
Connecticut Light & Power Co
Transmission or Distribution System Owner ID
4176
Transmission or Distribution System Owner State
CT
Grid Voltage (kV)
23
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:11468
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.