Power assets and projects · USA · eia860
Laredo Bus Facility Solar Canopies
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
20 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-d0107b7417ed431824032b5b
Detailed source fields
Original source field
Published value or condition
Utility ID
57441
Utility Name
MARTA
Plant Code
58064
Plant Name
Laredo Bus Facility Solar Canopies
Street Address
277 Laredo Dr.
City
Decatur
State
GA
Zip
30030
County
DeKalb
Latitude
33.783333
Longitude
-84.267778
NERC Region
SERC
Balancing Authority Code
SOCO
Balancing Authority Name
Southern Company Services, Inc. - Trans
Primary Purpose (NAICS Code)
485
Regulatory Status
NR
Sector
4
Sector Name
Commercial Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
Georgia Power Co
Transmission or Distribution System Owner ID
7140
Transmission or Distribution System Owner State
GA
Grid Voltage (kV)
20
Energy Storage
N
Natural Gas Storage
N
Liquefied Natural Gas Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:6056
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.