Power assets and projects · USA · eia860
North Brawley Geothermal Plant
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
92 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-8c12aff4e19de5ed67e18a53
Detailed source fields
Original source field
Published value or condition
Utility ID
34691
Utility Name
Ormat Nevada Inc
Plant Code
56832
Plant Name
North Brawley Geothermal Plant
Street Address
4982 Hovley Road
City
Brawley
State
CA
Zip
92250
County
Imperial
Latitude
33.0139
Longitude
-115.5439
NERC Region
WECC
Balancing Authority Code
IID
Balancing Authority Name
Imperial Irrigation District
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
Y
FERC Small Power Producer Docket Number
ER08-1574, ER10-2294
FERC Exempt Wholesale Generator Status
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
Imperial Irrigation District
Transmission or Distribution System Owner ID
9216
Transmission or Distribution System Owner State
CA
Grid Voltage (kV)
92
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:5038
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.