Power assets and projects · USA · eia860
Gastonia Duke Street
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
12.47 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-e4f79029dd4152e247dbae21
Detailed source fields
Original source field
Published value or condition
Utility ID
13630
Utility Name
North Carolina Mun Power Agny #1
Plant Code
56061
Plant Name
Gastonia Duke Street
Street Address
3040 Duke Street
City
Gastonia
State
NC
Zip
28052
County
Gaston
Latitude
35.223381
Longitude
-81.13306
NERC Region
SERC
Balancing Authority Code
DUK
Balancing Authority Name
Duke Energy Carolinas
Primary Purpose (NAICS Code)
22
Regulatory Status
RE
Sector
1
Sector Name
Electric Utility
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
City of Gastonia
Transmission or Distribution System Owner ID
7027
Transmission or Distribution System Owner State
NC
Grid Voltage (kV)
12.47
Energy Storage
N
Natural Gas Storage
N
Liquefied Natural Gas Storage
X
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:4480
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05