Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Boulder City Betasso Hydro Plant
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
25 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-0311249d0b60408e8f937217
Detailed source fields
Original source field
Published value or condition
Utility ID
1994
Utility Name
Boulder, City of - (CO)
Plant Code
54680
Plant Name
Boulder City Betasso Hydro Plant
Street Address
1094 Betasso Drive
City
Boulder
State
CO
Zip
80306
County
Boulder
Latitude
40.0111
Longitude
-105.3347
NERC Region
WECC
Balancing Authority Code
PSCO
Balancing Authority Name
Public Service Company of Colorado
Name of Water Source
Middle Boulder Creek
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
Public Service Co of Colorado
Transmission or Distribution System Owner ID
15466
Transmission or Distribution System Owner State
CO
Grid Voltage (kV)
25
Energy Storage
N
Natural Gas Storage
X
Liquefied Natural Gas Storage
X
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:3826
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.